Revised 6 Sep 1999
Project Manager Don GettyA. PROJECT DESCRIPTION
Kentucky Lock is located in western
Kentucky at Mile 22.4 of the Tennessee River. A feasibility report
completed in 1992 recommended a new 110' x 1200' lock adjacent and
landward of the existing 110' x 600' lock. The project was authorized for
construction in WRDA 96. FY 98 funding of $4M was used to continue WES
model studies, the Lock DM, Transmission Tower DM, subsurface exploration,
and initiate the Railroad DM. Construction on the project was initiated
with the construction of an access road on the powerhouse island that was
completed in August 1998. Due to fiscal reprogramming efforts within the
Corps, the FY 99 funding plan of $12.6M is:
- $3.3M -- Lock DM
- $2.7M -- Railroad DM
- $1.9M -- Highway DM
- $0.7M -- Cofferdam DM
- $0.16M -- Materials DM
- $2.2M -- Transmission Tower
Relocation
- $0.6M -- Lock and Navigation
Models at WES
- $0.2M -- Environmental Studies
- $0.4M -- Construction Contracts
- $0.44M --
Management/Miscellaneous.
Subsurface exploration costs are
included in the costs for the DM’s above.
B. GENERAL
Homepage
-- Additions/improvements to KY Lock’s Homepage, www.orn.usace.army.mil/pao/kylock/
,
continued over the last month. A notable addition is updated pictures of
the lock model. An updated artist rendering showing the proposed
pedestrian/bike bridge over the locks is complete and will be shown on the
site in the near future.
Expenditures for the Fiscal Year
-- Through 31 August, the KY Lock expenditures were at 96% of scheduled
expenditures. We are on track to expend approximately $12.4M of the $12.6M
allocated to the project by 30 September, the end of the fiscal year.
Groundbreaking Ceremony (15 October
at 2:00 p.m.) -- The last
scheduled planning session for this event is to be held 15 September at
11:00 a.m. in Nashville.
Significant issues raised and
decisions made during the month on the project include:
- Pedestrian/bike corridor
- The preferred corridor across the dam was selected. This path will be
on the to-be-abandoned RR bridge across the powerhouse and spillway
bays.
- Powerhouse island access ramp
-- The alignment for this ramp was selected. It will result in the
relocation of a TVA warehouse.
- Highway embankment side slopes
-- The design side slope of 3H:1V was chosen by the design team --
allowing the design of many critical features to proceed.
- West bank bridge approach
embankment construction contracts
-- It was originally planned to advertised for a construction contract
just for the joint Hwy/RR embankment on the west bank in the January 2000
timeframe. Due to delays in this embankment’s contract P&S,
advertising for the entire Hwy/RR west bank embankment in the March/April
2000 timeframe through the advancement of the highway embankment design
effort is being considered.
C. PROGRESS FOR THE MONTH:
Environmental
Environmental Coordination
-- A meeting is tentatively scheduled for 13 September in Cookeville, TN
to meet with the US Fish and Wildlife Service regarding the recently
submitted biological assessment. In-house efforts are continuing in the
development of the Environmental Assessment for the highway relocation.
WES Visit
- A meeting at WES (Vicksburg) to view existing conditions in the
navigation model and to discuss upcoming tests was held on 19 August
(minutes available the week of 7 Sept). Representatives of the KY Dept. of
Fish and Wildlife and the US F&W attended along with Corps and TVA
personnel. Significant observations/discussions/decisions made include:
Mussel velocity measurement sites
-- Seven transects were identified for measuring flow velocities on 250’
centers for existing versus proposed conditions.
Mooring cell locations
-- It continues to be apparent that locating the two proposed mooring
cells will be difficult without significantly impacting the mussel
resource. This issue will require continued analysis and discussion with
all the parties involved before resolution.
Gas supersaturation
-- Although the model cannot measure these levels, it can be used to
assess the mixing characteristics between the powerhouse discharges and
the spillway discharges through dye tests. Preliminary dye tests were
observed by the participants and these will be refined by WES personnel.
Tailwater eddy
-- This eddy that can draw recreational craft into the dangerous spill
area was accurately reproduced by the model.
Training dikes
-- Different configurations for these possible dikes were discussed. If
selected for incorporation into the project, it is hoped that this dike(s)
will be beneficial to not only navigation conditions, but will also
enhance mixing, reduce the negative effects of the tailwater eddy, and
provide additional fish habitat.
Mussel mitigation
-- A discussion was held on possible mitigation plans for the loss of
mussel habitat due to the project.
Cultural Resources Assessment --
The planned coordination meeting with the Kentucky State Historic
Preservation Officer was cancelled due to an earlier visit to the site by
the SHPO’s office. A site visit by Duvall and Associates is scheduled
for the month of September.
Exploration
The Nashville District’s Drill
Crew has completed 36 of
the 39 holes to be drilled on the east bank (EB) Hwy 62 alignment. The
remaining 3 holes will be drilled by a contract crew. The Nashville
District crew will return to the site the week of 20 September to obtain
additional rock information at two holes at the abutments of the Hwy
bridge over the RR.
Overwater drilling
commenced by Harza/H.C. Nutting on 10 August. Holes completed as of 3
Sept. include all 8 for the overwater Hwy bridge, all 5 for the downstream
cofferdam, both holes for the possible, temporary truss bents, and 2 of 3
holes for the upstream approach walls. It now appears that the Hwy and RR
pier holes located near the bank will be drilled from the barge instead of
the previously anticipated land bridge.
Testing
-- A task order was awarded to FMSM on 24 August to perform all the
geotechnical testing for the remainder of the drilled samples.
WES Navigation Model
August meetings
- Two meetings were held at WES to view the model, review the existing
condition results, and discuss future tests. The first meeting on 19
August concentrated on environmental interests (see description in
Environmental above). The second meeting on 20 August involved
navigation interests (minutes available the week of 7 Sept). There was a
consensus by the industry representatives that the model accurately
depicts existing navigation conditions. It was proposed in this
navigation meeting that one of the five TW/flow combinations be dropped
from study and two combinations be added. This proposal is being
evaluated by LRN and WES and will be distributed for review by all
interested parties prior to a decision. The location of the two proposed
mooring cells was also discussed. A location downstream of I-24 seemed
to be preferred. A proposal to replace the two mooring buoys downstream
of I-24 with the mooring cells will be considered in the modeling but
may be too far downstream to be accurately modeled.
Next meeting
-- After the many changes/additions to the testing schedule proposed in
the 19 and 20 August meetings, the model testing schedule will have to be
revised. The best guess now is that the next meeting will be scheduled in
the January 2000 timeframe. The next visit will view proposed conditions
with possible training dike configurations in conjunction with the piers
for the two new bridges.
WES Lock Model
Testing of the new upstream
topography and the upstream floating guardwall are the last planned tests
for this model. The tests are anticipated for this fall. New pictures of
this model are on the KY Lock website.
Lock Design
In-house
efforts continue to focus on the support of WES’s Lock and Navigation
Model work, new lock stability, miter gate design, culvert valve design,
preliminary electrical/mechanical design, east bank permanent
embankment, and the development and managing of task orders.
Electrical/Mechanical Design.
A 20% progress conference call was held on 18 August for this design
effort. Harza’s 25% submittal and a progress meeting are planned for
late Sept/early Oct.
Site Design
-- In lieu of one task order on this effort, three are now underway in an
attempt to expedite this feature. Two task orders have been negotiated
with Gresham Smith & Partners (GS&P) to development DM level
designs for the site development and for the site architecture. The third
task order will be negotiated with Harza the week of 7 September for the
architecture of the proposed operations building and the operator stands.
A kick-off site visit for this effort was made on 1 Sept. In-house efforts
are underway to define the cut lines for the excavation during lock
construction. This information is expected to be sent to GS&P the week
of 7 Sept for their use in siting structures.
Visitor Center -- A
conference call that involved TVA, Corps, and GS&P representatives was
held on 3 Sept. The purpose of the call was to coordinate design roles and
discuss partnering possibilities for the proposed visitor center. It was
agreed that a limited meeting will be planned at the KY Fish and Wildlife
Department’s visitor center in Frankfort, KY for the purpose of
exploring partnering possibilities with the KY F&W Dept, probably in
late September. A second meeting will be held later at KY Lock with all
other possible entities that will have an interest in the center. Avis
Kennedy of LRNCO-T is continuing in her efforts to obtain guidance from
higher Corps authority on whether and how the visitor center can be
included as part of the project.
Lower Guidewall --
A 70% review meeting on this DM level effort was held on 1 September with
Harza Engineers in Chicago (minutes not yet available). Significant
discussions include:
Foundation treatment
-- In the 95% submission, Harza will include additional analyses and
treatment schemes for the anticipated limestone cavities to be encountered
by the drilled shaft and diaphragm wall foundations.
Tremie concrete QC
-- The 95% submittal should include plans and costs for
minimizing/locating voids for tremie concrete placement.
Construction techniques
-- Discussions were held on possible construction techniques for the
drilled shafts (no permanent steel casing to allow for soil side friction
development), diaphragm wall (panel lengths and excavation methods), and
lower fender section (pre-cast panels are to be examined for minimizing
forming/placement of concrete below water levels).
RCC strengths
-- Preliminary results of the roller compacted concrete mixes are showing
lower than expected compression strengths and higher than expected modulus
of elasticity. Harza will provide recommendations to deal with these
issues in the 95% submission. Although these unexpected results are not
expected to significantly impact the design of the lower guidewall, they
could have ramifications for the possible use of RCC in the lock walls.
Cost estimates
-- The cost estimate and contingencies in the 95% submittal will reflect
the concerns, unknowns, and construction techniques discussed in the
meeting and noted in the comments.
TVA Board of Consultants
-- A presentation on this wall’s design will probably be made to the TVA
Board of Consultants’ meeting the week of 16 November. A meeting with
TVA staff will be incorporated into the 95% meeting in Nashville planned
for October.
Upper Approach Walls
- A task order to advance the upstream guardwall to DM level was planned
for INCA Engineers. Due to the size of this task order and the proximity
of the end of the FY, a decision was made to postpone it until the
beginning of next FY.
Floating Caisson--
A 95% submission on this DM level effort by INCA is expected the week of 7
Sept.
Miter Gate Design
-- Design efforts using a finite element model for the gates is ongoing
by LRL. A 75% submission by LRL is expected soon. A task order to INCA
to provide design checks was awarded by LRN. It is planned for LRL
design representatives to attend the next Elec/Mech meeting in Chicago
in early October to coordinate design efforts.
As-built Drawings
-- A 50% submission by AIMSI Engineers on this task order is expected in
September.
EB Permanent Embankment
-- The in-house DM level design of this feature is still ongoing and is
being refined to develop excavation cut limits.
Project Utilities
-- A task order is planned for next FY to prepare the designs for all
the utilities affected by the project that are not currently assigned to
a design team.
EP-D New IDT’s
- Contracts have now been awarded to all four of the new lock A/E’s.
They are 1) Black and Veatch, 2) a joint venture of INCA/RW Beck/Stone
& Webster, 3) a joint venture of Bergmann Associates/ Ben C. Gerwick,
Inc., and 4) Harza Engineers.
Disposal/Contractor Laydown Areas
Vulcan Materials Disposal Site
-- Activities necessary to acquire the real estate rights for this
46-acre site located about ¾ mile from the proposed lock on Hwy 453
have been initiated. These include:
- A task order has been scoped
and will be negotiated the week of 7 Sept to Bergmann Associates/Ben C. Gerwick (BA/BCG) to develop necessary designs for this disposal site. This
includes access roads, storm water and erosion control measures, volumetric determinations, staging arrangements,
assessment of
impacted utilities, and final site characteristics.
- A site and boundary survey was
initiated by American Engineers the week if 9 August and will be
completed this month.
- A decision has not yet been
made on whether to acquire this
property in fee or to obtain a long-term easement from Vulcan
Materials Corp. No discussions between TVA and the Corps have
been held on this issue since the 4 August meeting with Vulcan
officials. Since it is planned for TVA to obtain an appraisal for
this
property this fall, it may be beneficial to postpone this decision
until
after receipt of the appraisal.
Cofferdam DM
Downstream cofferdam
-- A 70% submission on this DM level effort is expected from Harza by
the end of September. An economic report recommending a top elevation of
342’ for this cofferdam was received from Harza on 3 September. A
review of this report by the design team will be necessary before a
final decision can be made on this design top elevation. A presentation
on this design is expected to be made to the TVA Board of Consultants at
their meeting the week of 16 November.
Upstream cofferdam
-- Scoping efforts on this DM level design effort are complete and
negotiations for this task order to B&V are expected the week of 7
Sept.
Independent Technical Review
-- A draft scope has been developed and coordination efforts are underway
by LRN’s Structural Section and Geotechnical Branch to assemble this
review team.
Value Engineering Study
-- To support the downstream cofferdam VE team, a task order has been
negotiated for BA/BCG to provide the technical designs for at least two
alternative concepts to those presented in Harza’s 30% D/S Cofferdam
report. BA/BCG is examining both a float-in wall/cofferdam section and a
full-width, braced cofferdam that will have a precast interior wall panel.
Materials DM
Testing of the sand and rock
samples are ongoing at the Waterways Experiment Station (WES) and
completion is expected in October.
Hwy/RR
Quarterly Design Meetings --
The highway and railroad quarterly design meetings were held on 16-17
August (minutes available soon). Significant discussions at the joint
meeting include:
- All drilled shafts will probably
be constructed in a plumb configuration.
- Circular pier cap
-- Hanson was asked to change the RR’s rectangular cap to circular to
match the Hwy design. However, recent cost concerns over the circular
cap have caused this issue to resurface.
- Wider boat basin
-- Preliminary thoughts about the bridge contractor using the existing
boat basin on the left bank as access to the river were diminished when
it was determined that sufficient width and draft were not available
during low water periods. It was agreed that widening and deepening this
basin will be examined for its cost/feasibility. If this widening is
feasible, then this will probably postpone the construction of the
recreational boat ramp planned for this fall by TVA forces. However, the
planned paving of the downstream parking lot will be pursued next FY if
funds are available.
- Hanson and ACE should provide
pier/drilled shaft designs to LRN by October so they can be
incorporated into the Navigation Model.
- LRN will be responsible for
additional horizontal and vertical control analysis at the project
site.
- The EB highway alignment will
not require retaining walls at the transmission towers as thought
earlier.
Temporary bents in navigation
canal -- After analyzing
various possible truss erection bents in the navigation canal, it was
determined that an acceptable configuration had not been developed. The
specifications for the construction contract will not allow any type of
falsework that will negatively impact navigation; therefore, the truss
will likely have to be floated into place. Preliminary indications are
that this will add a 30% premium to the steel erection costs as compared
to using falsework.
WB Joint embankment contract
-- The advertising for this contract will be delayed from its planned
January 2000 date due to various delays in the design process. It will
probably be delayed on the order of several months.
Hanson’s contract will be
modified to allow for the submission of the US Coast Guard permit ASAP.
TVA still has information to send to Hanson before they can complete the
303(b) analysis.
LRN and TVA will develop a wetlands
mitigation plan whose scope will be dependent on the final footprint of
the Hwy and RR relocations.
The next quarterly design meeting
is scheduled for 1-2 November at the Lake Barkley Resource Managers
office. The RR-only meeting is scheduled for the afternoon of 1 November.
The joint Hwy/RR meeting is scheduled for the morning of 2 November and
the Hwy-only meeting that afternoon.
Highway DM
Quarterly Design Meeting -- Significant
discussions at this 16 August meeting include:
- The plate girder alternate for
the navigation span is now being designed as a counterbalanced
structure to reduce costs.
- Seismic criteria will be
reevaluated and refined.
- FMSM will provide a schedule for
geotechnical test results.
- It is expected that TVA will
only assume maintenance responsibilities for the highway embankment
that has dam safety implications. This is only a short reach near the
west bank tie-in. The maintenance for the remainder of the embankment
will be the responsibility of the KTC, which usually does not perform
regular mowing of high embankments such as this.
- ACE will analyze the costs of
3:1 and 4:1 embankment side slopes in an effort to reach a design
decision.
Pedestrian/bike bridge type
-- After discussing three different bridge types, it was agreed that a
cable-stayed alternative would be developed for final design. Its
alignment will probably be downstream of the middle wall maintenance
bridge due to the location of the stoplog slots.
Pedestrian/bike corridor
-- After discussing the deficiencies in the existing Hwy 62 bridge across
the dam and the costs of alternative alignments, it was agreed that the
pedestrian/bike path should be constructed on the to-be-abandoned RR
bridge across the spillway and powerhouse.
Pedestrian/bike safety
-- ACE agreed to investigate alternative fencing/barriers that will
provide for the safety of users and those below the bridges and also be
aesthetically acceptable.
Powerhouse Island Access Ramp
-- ACE presented 6 alternative alignments for consideration. After
concerns about retaining wall heights were raised, it was agreed to select
the alignment with the widest curvature for final design. This alignment
will result in the relocation of a TVA warehouse to a location downstream
of the switchyard.
Middle wall maintenance bridge
-- A site visit to the lock was made to develop design constraints for
this bridge whose centerline has been moved downstream due to concerns
about its interference with the placement of chamber stoplogs. ACE will
develop additional designs based on these new constraints.
DM Design
-- In addition to those designs presented at the quarterly meeting,
activities performed during the month by American Consulting Engineers
(ACE) include:
- Navigation Span
- Developed and prepared
quantities for three truss configurations.
- Continued development of
counterbalance plate girder design with estimated savings of $1.6M
over previous concepts.
- Continued analysis of 304’ vs.
152’ viaduct spans.
- Continued seismic analysis of
deep water foundations.
- Continued development of middle
wall access bridge.
- Researched and developed
preliminary designs for isolation bearings.
- Completed field survey of cross
sections and profile.
- Completed side slope and
guardrail analysis and submitted to KTC on 19 August. On 30 August,
received approval from KTC for 3H:1V side slope with guardrail
section.
- Completed revisions to approach
roads recommended at quarterly meeting.
- Continued work on US 62 plans
including the incorporation of the 3:1 side slopes.
- Continued on generating
computerized rendering of the site. Navigation span alternates are now
complete.
Coordination with the Kentucky
Transportation Cabinet. LRN
has submitted a first draft of a betterment sharing agreement with the
KyTC to TVA for review. An exhibit to this agreement will be the
computations that determine the cost share between the Corps and the KTC.
The KTC has been contacted and is sending their computations developed
last year to the Corps. ACE has also been asked to develop these cost
share percentages based on the design to date.
Railroad DM
Quarterly Meeting -- Significant
discussions at this meeting (draft minutes available) include:
- Foundation and pier types for
both of the navigation span piers were determined.
- Approach span pier foundations
-- The four 6’-6" diameter drilled shaft arrangement was
preferred by the P&L RR over the single shaft design.
- RR Bridge over Hwy 282
-- Three alternative designs were presented for this bridge. After a
discussion of the pros and cons, the thru-plate girder alternative was
selected for final design. A 6" vertical clearance variance will be
sought from the KTC for this alternative.
- Parameters, options and model
testing of the proposed protection scheme for the island pier were
discussed.
- A side slope of 2.5H:1V with
grassed slopes was chosen for the embankments.
- Vulcan Materials Haul Road Box
Bridge Modification --
Representatives of Vulcan Materials Corp. attended this session of the
meeting to discuss this feature on which they may want to betterment
share. The current double box under the P&L RR does not provide
sufficient horizontal and vertical clearance for their future needs.
Hanson had provided a 75% complete report for review prior to the
meeting that presented design and cost information on variations of five
alternatives. These alternatives were discussed in detail at the
meeting. Since Vulcan’s betterment share for these improvements was
much greater than they felt was obtainable from their budget, the
parameters for a planned sixth alternative were agreed upon. This sixth
alternative has the potential of cost savings over the previously
studied alternatives.
- Walker Cemetery Access Road -- The
Plans and Specifications for this road were transmitted to the 8A
contractor on 10 August and a fee proposal is expected by 10 September,
with negotiations to follow shortly thereafter. A pre-bid walk through
at the site with the contractor was held on 31 August.
RR Design
-- In addition to the items listed in the quarterly meeting, Hanson
Engineers have performed the following activities over the last month:
- Completed preliminary design of
the truss span
- Completed study of the
modification of the RR bridge over KY 282
- Continued the collection of
information for MCACES cost estimates
- Continued the Section 303
(formerly 4(f)) Statement
- Continued preliminary foundation
design for approach spans
- Initiated efforts on 50%
submittal of Design Memorandum.
- Continued efforts on WB water
and sewer line P&S.
Geotechnical Design
-- Harza submitted their 100% DM geotechnical report in KTC format for
their review. A task order was be issued to Harza to complete geotechnical
studies for P&S on the WB embankment.
TVA Transmission Towers Relocation
Eight Upstream Towers (four on
each bank) -- A scoping
meeting to discuss the current status and future gameplan for the
construction of these eight towers was held on 23 August in Chatanooga.
Significant discussions include:
- The Corps is in the process of
seeking approval by the Assistant Secretary of the Army (Civil Works)
to allow TVA to use members of its contract partners in the
construction of the towers. It is not expected that approval will be
obtained until at least November 1999.
- Truck loads of the structural
steel, H-piles for the load test, and associated hardware to construct
the eight towers has been arriving at the site and should be
completely stockpiled by the end of September.
- The design/alignment of
grounding cables across the canal and relocation of wooden power poles
are issues that still have to be addressed.
- The use of barges for assembly
platforms is probably not practical for the island towers.
- The vertical clearance and
construction sequencing of the transmission line relocation in
conjunction with the construction of the downstream cofferdam still
requires substantial coordination.
Preliminary Design/Construction
Schedule:
10 Sept 1999 -- Issue Contract
Drawings for EB tower foundations. LRN to initiate review and
development of Contract Documents.
Early December 1999 -- Begin
load test for 6 H-piles for downstream most tower on the powerhouse
island. To be performed by TVA Heavy Equipment group and TVA contract
partners.
Early December 2000 -- Notice
to proceed for Corps 8A contractor to construct EB tower foundations.
Footings for all four towers completed by the end of spring 2000.
Early January 2000 -- TVA HE
group begin pile driving for upstream most tower on powerhouse island.
Complete pile driving for all four towers on PH island by 31 May 2000.
July/August 2000 -- TVA tower
assembly group will initiate tower erection. By December 2000, will
complete two upstream towers on both the EB and on the PH island as
well as the line transfers.
March 2001 -- TVA tower
assembly group resumes tower erection for last four towers. Completes
all four and line transfers by 31 May 2001.
Three Downstream Towers (69 kV)
-- Approval of the proposed retaining wall scheme to eliminate the need
to relocate these three towers has been granted by TVA and Corps
reviewers. Ongoing stability analyses are required to complete this
design.
Miscellaneous
Development of Drawing Library
System -- LRN plans to
develop a library of all drawings that can be accessed by all members of
the design team. When it is complete, a message will be sent to all
design team members and will be posted on the Homepage.
KY Lock Telephone Directory
-- Download a list of all organizations and key personnel involved in the design
of this project that contains their address, phone numbers and email
addresses:
Microsoft
Access Format
Microsoft Excel Format
Print copies available upon request to Don Getty, (615) 736-2346 don.b.getty@usace.army.mil.
|