|
Revised 8 March 2002
PM Don Getty
A.
PROJECT DESCRIPTION
Kentucky
Lock is located in western Kentucky at Mile 22.4 of the Tennessee River. A feasibility report completed in 1992 recommended a new 110'
x 1200' lock adjacent and landward of the existing 110' x 600' lock.
The project was authorized for construction in WRDA 96 and
construction commenced in July 1998.
B.
GENERAL
Significant
activities, issues raised, and decisions made during the month on the
project include
:
Construction
activities:
·
Upstream
Cofferdam –
C.
J. Mahan completed the initial phase of dry excavation and constructed a
causeway for grouting operations in February.
Drilling operations for the grout lines commenced the week of 4
March. Grouting activities
should be the predominant activities into June.
Scheduled completion date for this $11.3M contract is January 2004.
·
Bridge
Substructures
–
C.J. Mahan completed excavation for the west bank railroad piers of
R1 and R2 this month, and pile driving for R2 commenced the week of 4
March. During excavation of
R2, timber piles were uncovered from the abutment of the ICG railroad
bridge that was abandoned in the mid 1940’s.
It is expected that these wooden piles will not significantly
affect pile driving for this pier. Current
plans are to commence mobilization for marine operations in April.
Scheduled completion date for this $36.6M contract is April 2004.
·
TVA
Transmission Towers
– Final
testing of the soil anchors on the temporary retaining wall were completed
this month. TVA’s Heavy
Equipment Division is expected back on site in March to perform the minor
earthwork necessary to complete this wall.
·
West
Bank Hwy/RR Embankment
– Wet and cold weather over the last few months have prevented any
significant activities on the embankment construction by Murray Paving.
It is expected that embankment construction will restart by the end
of March if Mother Nature cooperates.
This $5.9M contract is over 80% complete.
·
Benton Wetlands – Issuing the notice to proceed on this contract is being deferred
until dryer weather will allow site grading to commence.
C.
PROGRESS FOR THE MONTH:
Environmental/Recreation
·
Mussel
Mitigation
–
·
Lake
Survey Reports – The 95% report on the surveys performed in Barkley and
Kentucky Lakes are still under review.
·
Tailwater
data compilation – The 95% submittal on this work is under review.
·
Tailwater
Fishing Mitigation
(West Bank Jetties) – Protracted efforts are continuing to modify
Murray Paving’s contract to have the jetties constructed.
WES
Navigation Model
Status
– A draft final report is currently under review.
WES
Lock Model
A draft report documenting the conditions due to the
new short approach wall is under development.
Lock
Design
In-house.
The main focus of in-house resources is to manage A/E
contracts and continue in-house design efforts.
Work is continuing on:
-
Culvert Bulkhead Air Seal design, Recess fillers, ladders, mooring bit
recess metals, and handrail.
-
Engineers are working to draft concrete material and mix specifications.
-
Middle wall fill containment structures for the upstream and downstream
areas are being designed.
-
P&S on lock lighting and floating mooring bits.
-
Value Engineering Studies for the Upstream Floating Approach Wall are
underway. During the week of
4 March, the VE team made a site visit to Olmsted and its casting yard
where they are constructing Olmsted’s floating approach walls that are
similar to those currently proposed for KY Lock’s upstream walls.
A significant result of the site visit was the refinement of unit
prices for the concrete work.
Miter
Gate Design. Louisville District has completed P&S design of the miter
gates. INCA has completed the
engineer’s check of the P&S and supplied comments to LRL. LRL designers are wrapping up revisions to the design from
these computation checks.
Site Utilities – Review comments
for the 95% Design Memorandum submittal were provided to MWH and revisions
are underway. MWH has
initiated P&S portion of the U/S Lock Excavation site utilities.
Upstream
Monolith Design – In February, Black & Veatch transmitted their 70%
submittal on the DM level design of the Upstream Lock Monoliths.
This submittal includes the final stability analysis and the
thermal analysis (including both parametric studies and cracking
analysis). B&V has
initiated a stress analysis of the upstream monoliths which will include
design of the reinforcing. A
review meeting for the 70% submittal is scheduled for 19 March at KY Lock.
Downstream
Lock Design
- Huntington District transmitted their 50% progress submittal
on the downstream monolith Phase I designs in late Feb. This submittal includes monolith stability and geometry
refinements. A comment
resolution and coordination meeting is planned at the KY Lock site after
review.
New Operations
Building & Maintenance Complex –
MWH’s
is incorporating the decisions from 60% comments into their next
submittal.
East Bank Roadways/Site Plan P&S
– American Consulting Engineers submitted a revised folio for
the east bank roadways and site plan at the 12 Feb. 2002 review meeting
(minutes available). Significant
decisions made at the meeting include:
·
The
main intersection will not be offset and will include stop signs for the
Ferry Landing road and the Operations Access road.
This configuration will require design changes to ensure that
traffic is calmed prior to entering the public parking lot.
·
The
final east bank embankment’s top elevation will remain at elevation
388.0 but its alignment for tie-in to high ground has not been finalized.
·
The
plaza concept was abandoned due to many technical hurdles that were going
to be costly to overcome. It
will be replaced by a “gathering area” that will be located adjacent
to the public parking lot.
·
A
cart path will be added from the new maintenance compound to the new
lock’s landwall.
Disposal/Contractor
Laydown Areas
Vulcan
Materials Disposal Site – No activities on this feature have occurred in the last month.
Cofferdam
Design
Downstream
cofferdam
- The Downstream Cofferdam A-E’s, Bergmann/Gerwick/D'Appolonia,
were in Nashville on 8 January to discuss comment responses to the 70%
P&S design submittal (minutes available).
The meeting highlighted the need for Nashville to coordinate
concrete specifications and connection of the cofferdam to future lock
structures being designed by others.
Efforts are underway to issue a task order to B/G/D’A to complete
the P&S for this cofferdam.
Materials
DM
WES is continuing testing on concrete mixes and
aggregates.
Relocations
·
RR/Hwy
Design
·
East Bank Approaches – A 96% submission on Specifications was made in
January and a review meeting was held on 11 Feb. Major decisions/discussions at the meeting were:
·
Riprap
gradations to be specified were confirmed.
·
A
detention basin was added to the drainage design.
·
Payment
methods for the excavation of unsuitable material was discussed.
·
It
was decided to keep the original design of the retaining wall for tower
No. 1.
·
West Bank RR Embankment Extension Modification
– Efforts are continuing in modifying Murray Paving’s contract to
perform this work.
·
Superstructure Design – Negotiation
efforts with Hanson for developing P&S for the railroad superstructure
have been completed and a contract modification should be awarded in
March. A superstructure
coordination meeting was held on 12 Feb.
Significant decisions/discussions at the meeting include:
·
Coordination
efforts and data collection efforts with Vulcan Materials need to be
re-initiated in conjunction with final design efforts for modifying
Vulcan’s box bridge under P&L RR.
·
Hanson
and ACE will be applying for FAA permits for the bridges.
·
Details
to get W. KY Rural Electric Power to the east bank abutment of the new RR
bridge need to be developed.
·
A
decision on the limits of removal of the existing WB RR embankment is
still pending and will possibly impact access to underground utilities.
·
Criteria
for safety features associated with inspection of the new RR bridge were
agreed upon.
Miscellaneous
KY Lock
Telephone Directory – A list of all organizations and key personnel involved in the
design of this project that contains their address, phone numbers and
email addresses is available upon request to Don Getty, (615) 736-2346 [don.b.getty@lrn02.usace.army.mil].
Future
Project Meetings
·
19
March – 70% Review meeting on U/S Lock Monoliths at BAR/R.
·
22
March, 0930 – Instrumentation coordination meeting at Nashville District
·
22
March 0800 – U/S Lock Excavation coordination meeting at Nashville
District
End
of Report |