Revised 3 July 2001
PM Don Getty
A. PROJECT DESCRIPTION
Kentucky
Lock is located in western Kentucky at Mile 22.4 of the Tennessee River.
A feasibility report completed in 1992 recommended a new 110' x
1200' lock adjacent and landward of the existing 110' x 600' lock.
The project was authorized for construction in WRDA 96 and
construction commenced in July 1998. Based
on an expected funding level of $25.2M (Appropriated $30M minus Savings
& Slippage), our FY 01 spending plan is provided below:
$ 4.5M
In-house design and management
$ 1.2M
Other Corps
$ 0.5M
TVA in-house
$ 7.5M
A/E Contract Design
$11.5M
Construction and Real Estate Acquisition.
B.
GENERAL
Significant activities, issues raised, and decisions made during the
month on the project include :
·
Upcoming Construction
Contracts Our plans to
initiate four construction contracts within the next few months are on
track. The Upstream Cofferdam
was advertised on July 2nd with a bid opening scheduled for
August 16th. A
pre-bid meeting at the site for potential bidders is scheduled for July 25th.
The Bridge Piers are scheduled for advertisement within the week and
a pre-bid meeting is scheduled for July 26th.
The Construction Field Office and the Wetlands at Benton are planned
to be negotiated contracts that should be issued in the July/August
timeframe.
·
Final Supplemental
Environmental Impact Statement and Record of Decision
The suspense date for comments on the Final SEIS is 9 July.
All agency coordination necessary for the ROD to be signed has been
completed including the 401 Water Quality Certification, the Fish and
Wildlife Coordination Act Report, and resolution of comments from US EPA
Region IV. Barring the receipt
of significant comments, it is anticipated that the Division Commander will
sign the ROD the week of 9 July.
Construction activities:
·
TVA Transmission
Towers Work is
progressing on the fourth and final tower on the east bank.
·
West Bank Hwy/RR
Embankment Murray Paving continued significant construction
activities in June. Most of
their work efforts centered on constructing the combined embankment located
to the east of the existing railroad embankment.
This $5.9M contract is approximately 26% complete.
C.
PROGRESS FOR THE MONTH:
Environmental
·
Supplemental
Environmental Impact Statement
See Significant Activities under B.
·
Wetland Mitigation
- The final P&S package
has been submitted by Hanson Engineers and contract packaging is ongoing.
A construction contract is planned to be initiated this summer.
·
Mussel Mitigation
The underwater
survey work for Kentucky Lake has been completed and report compilation is
ongoing.
·
Tailwater Fishing
Mitigation The contract plans have been completed and contract
packaging is ongoing. Construction
of the jetties is anticipated to commence as soon as possible after the
FSEIS Record of Decision is signed. A
mussel relocation effort of the jetties footprint is scheduled to
commence on 12 July.
WES Navigation
Model
Status A draft final report is currently under review.
WES Lock Model
Testing with the new upstream
middle wall location has begun at WES.
Significant vortices occurred during testing and WES is looking at
alternatives to mitigate this adverse condition.
Lock Design
In-house. The main
focus of in-house resources is to manage A/E contracts and initiate the new
construction contracts mentioned in section B above.
Work is continuing on the geotechnical drilling program, the support
of WESs Lock Model work, new lock stability, existing lock lower land
wall stability, miter gate design, lock intake trashrack design, the
Materials DM, and the east bank permanent embankment.
Electrical/Mechanical Design.
The 95% submittal of this DM was delivered approximately 15 May.
In-house review has been completed.
The Task Order will be completed this summer.
Upper Approach Walls The
90% submittal of the Phase 1 Design Report was delivered in May.
A comment resolution meeting was held on 12 June and the final
report is scheduled for submittal in July.
The over water drilling at the new middle wall nose pier location
was completed during the existing lock maintenance closure.
Results from the drilling and testing will be available soon.
Miter Gate Design.
Louisville District is putting together a final check set of the
Plans & Specifications for review by INCA.
Plans & Specs will be complete later this summer after INCAs
review.
Site Utilities The 70% submittal is expected any day, with the
final report completed by the end of the fiscal year.
Site Seismic Criteria The final submittal on this report was
received from MWH in June.
Upstream Monolith Design Complications with the stability
analysis have been worked out and Black & Veatch is continuing their
design.
Downstream Lock Design - Huntington
District is continuing work toward a 30% DDR submittal this FY.
Demolition and Modification of Existing Operations Building
The
95% submittal of Plans & Specifications was received in June.
Review is wrapping up and this design will be complete later this
summer.
New Operations Building Negotiations for this task order for
P&S of this facility and the new Maintenance building were completed in
June. Since close coordination
will be required with the East Bank Roadways/Site Plan effort, a joint kick
off meeting was held on June 13 and 14 at Barkley Resource Managers Office.
East Bank Roadways/Site
Plan P&S Efforts have been initiated to issue a modification to
ACE to prepare P&S for the parking lots, roadways, and site grading for
the east bank area of the lock. This
will require close coordination with the two buildings being designed by
Harza above. A combined
kick-off meeting on these two efforts was held on June 13.
Transmission
Towers
Construction progress See Construction Activities in Section B.
Retaining wall for three downstream, east bank 69 kV towers
TVAs Heavy Equipment Division tentative start date for this
construction is the week of 16 July 2001.
Disposal/Contractor
Laydown Areas
Vulcan Materials Disposal Site Comments on the 100% submittal
have been delivered and a final submittal is expected by 8 June.
Cofferdam
Design
Downstream cofferdam Negotiations
are currently underway for final P&S for this feature.
Members of the Bergmann/Gerwick design team visited the existing
lock dewatering to observe lock floor conditions to be encountered during
construction.
East Bank Temporary Cut-off Analysis The final report was submitted in June.
Materials DM
WES is continuing testing on
concrete mixes. We are still
on schedule to issue an essentially complete report at the beginning of FY
02. Reports on some testing
continuing past this date will be issued as an addendum to the report.
Relocations
·
RR/Hwy Design
·
Most of the design
teams focus over the last month has been to get the Substructure
Contract ready for advertisement. Efforts
are continuing to develop the scope of works for ACE and HEI to prepare
P&S for the Superstructure Contract.
Miscellaneous
KY Lock Telephone Directory A list of all organizations and key
personnel involved in the design of this project that contains their
address, phone numbers and email addresses is available upon request to Don
Getty, (615) 736-2346 [don.b.getty@lrn02.usace.army.mil].
Future Project
Meetings
·
July 25 Contractors pre-bid meeting on Upstream Cofferdam
·
July 26 Contractors pre-bid meeting on Bridge
Substructures
·
July 27 Meeting with local quarries on stone and
aggregate specifications
End of Report |