|
































|
Revised 2 July 1999
PM Don GettyA. PROJECT DESCRIPTION
Kentucky Lock is located in western Kentucky at Mile 22.4 of
the Tennessee River. A feasibility report completed in 1992 recommended a new 110' x 1200'
lock adjacent and landward of the existing 110' x 600' lock. The project was authorized
for construction in WRDA 96. FY 98 funding of $4M was used to continue WES model studies,
the Lock DM, Transmission Tower DM, subsurface exploration, and initiate the Railroad DM.
Construction on the project was initiated with the construction of an access road on the
powerhouse island that was completed in August 1998. Due to fiscal reprogramming efforts
within the Corps, the FY 99 funding plan of $12.6M is:
- $3.3M Lock DM
- $2.7M Railroad DM
- $1.9M Highway DM
- $0.7M Cofferdam DM
- $0.16M Materials DM
- $2.2M Transmission Tower Relocation
- $0.6M Lock and Navigation Models at WES
- $0.2M Environmental Studies
- $0.4M Construction Contracts
- $0.44M Management/Miscellaneous.
Subsurface exploration costs are included in the costs for the
DMs above.
GENERAL
Homepage The basic architecture of KY Locks
Homepage, www.orn.usace.army.mil/pao/kylock/,
has been redesigned. Data will continue to be added to the site over the next few months.
If you have any suggestions for its improvement, please contact Dave Treadway at
615-736-7161 or Don Getty.
Updated Project Cost Estimate Here are the results
of the working estimate that was just completed:
- 1995 Estimate (all Federal) $395M
- 1995 Estimate in 1999 dollars (inflation adjustment) $440M
- 1999 Working level estimate (all Federal) $437M
- 1999 Working level estimate (KyTC share) $22.5M
Considering all of the design changes since 1995 (especially the
addition of the downstream Hwy 62 bridge), it is encouraging that the projects
Federal cost has essentially not risen over the last four years.
FY 00 Funding Outlook Here is what is known about KY
Locks funding levels for FY 00:
- Presidents Budget Submission $7.75M
- Senate Appropriations Sub-Committee $9.75M
- House Appropriations Sub-Committee No number developed
- Stated capability of Project $15M
- The stated capability of the project is the funding level required
to keep the projects completion date as early as possible.
C. PROGRESS FOR THE MONTH:
Environmental
Highway Environmental Assessment The draft biological
assessment is currently under review by TVA and the Corps and is scheduled to be
transmitted to the US Fish and Wildlife Service in early July. This schedule should allow
for the preparation and completion of an Environmental Assessment prior to the
advertisement for the construction of the West Bank RR/Hwy embankment early next winter.
Coordination meeting with the KY Division of Water and KY Dept.
of Fish and Wildlife A productive coordination meeting was held between the
Corps and these two agencies on 29 June in Frankfort, KY. The main purpose of the meeting
was to discuss the preparation of the Hwy EA and water quality certification for upcoming
construction activities. A secondary purpose was to update the agencies on the current
status of the project. Significant issues discussed included the proposed construction
methods for the bridge piers, development of mitigation plans for all mussels impacted by
both the Hwy and RR bridge piers, and mitigation plans for impacted wetlands. Water
quality certification is in effect for near term construction activities, including the
downstream boat ramp (and all activities included in the original EIS). However,
certification of the bridge pier work and other work below ordinary highwater is not in
effect until completion of the Hwy EA and the EIS supplement that is planned for next FY.
The EIS supplement cannot be developed until testing is complete on the navigation model
which will not be until this winter. A trip to WES (Vicksburg) to view existing conditions
in the navigation model is expected in the mid to late August timeframe.
Cultural Resources Assessment
A task order is being
developed for Duvall and Associates to complete the remaining cultural and historical
surveys and compliance tasks. This will include coordination efforts with the Kentucky
State Historic Preservation Officer and other appropriate agencies and groups. A scope has
been finalized and negotiations are expected in early July for this order.
Exploration
The Corps Drill Crew returned to the site on 29 June
after being off-site for several weeks. They have initiated drilling for the east bank
highway alignment. Most of the remaining land-based drilling identified for the project is
related to the Hwy 62 relocation.
Near term drilling and testing schedule:Near term drilling and testing schedule:
Early July A drill crew from the Vicksburg District is
expected to begin drilling along the Hwy alignment. All geotechnical testing of drilling
samples taken along the Hwy alignment will be performed by FMSM.
August Initiate overwater drilling by Harza for: 1) Hwy
bridge piers, 2) D/S cofferdam, 3) U/S approach walls drilled shafts, 4) possibly
downstream bent locations for truss assembly and 5) RR bridge piers 4 and 14 and
commensurate Hwy bridge piers (probably via land bridge).
WES Navigation Model
Construction of the model was essentially completed in June.
However, chronic problems with the main water supply pump have prevented the start of
testing efforts. These chronic problems were fixed the week of 28 June and calibration
testing is expected to commence on 6 July. After calibration and base conditions flows
have been finalized, a meeting with navigation and environmental interests will be held at
WES. It is now anticipated that this will occur in the mid to late August timeframe. When
a date is selected, interested parties will be notified and the dates will be posted on
the KY Lock Homepage. Construction photos of the navigation model can now be viewed from a
link on KY Locks homepage. LRN personnel visited KY Lock the week of 21 June to
calibrate one of the upstream cameras being used in the barge impact study.
WES Lock Model
LRN is nearing completion of finalizing the upstream
topography. This will be sent to WES in early July for incorporation into the Lock Model.
Testing of this new topography and the upstream floating guardwall are the last planned
tests for this model.
Lock Design
In-house efforts continue to focus on the support of
WESs Lock and Navigation Model work, existing lock stability, new lock stability,
miter gate design, culvert valve design, preliminary electrical/mechanical design, east
bank permanent embankment, and the development and managing of task orders.
Electrical/Mechanical Design - The 100%
Electrical/Mechanical Concept report has been received. A new task order to take the
electrical/mechanical designs to a DM level has been negotiated and is nearing award to
Harza. Electrical/Mechanical Design - The 100%
Electrical/Mechanical Concept report has been received. A new task order to take the
electrical/mechanical designs to a DM level has been negotiated and is nearing award to
Harza. Electrical/Mechanical Design - The 100%
Electrical/Mechanical Concept report has been received. A new task order to take the
electrical/mechanical designs to a DM level has been negotiated and is nearing award to
Harza. Electrical/Mechanical Design - The 100%
Electrical/Mechanical Concept report has been received. A new task order to take the
electrical/mechanical designs to a DM level has been negotiated and is nearing award to
Harza.
Site Development John Manor of LRN has completed
conceptual designs and drawings of the new locks site development (available upon
request). A task order is being developed with Gresham Smith and Partners to take this
conceptual design to a DM level design. A scope has been finalized and negotiations are
expected in early July. A meeting is still planned for sometime in July at the KY Fish and
Wildlife Departments visitor center in Frankfort, KY to explore the partnering
possibilities for KY Locks possible visitor center. Avis Kennedy of
LRNCO-T is
continuing in her efforts to obtain guidance from higher Corps authority on whether and
how the visitor center can be included as part of the project.
Lower Guidewall Design efforts by Harza for this
feature are slightly behind schedule due to delays in the RCC testing program, design
changes, and refinements in the rock profile. Even with these delays, essential completion
of this work effort is still expected by the end of the FY.
Upper Approach Walls - It is planned to issue a task order
to advance the upstream guardwall to DM level to one of EP-Ds new IDT Contractors
upon their selection (see below).
Floating Caisson After a successful review of the 30%
submittal on this DM level effort and a site visit to view the setting of the existing
floating caisson at Guntersville Lock, design work by INCA has continued and is on
schedule.
Miter Gate Design Design efforts by the Louisville
District Corps of Engineers (LRL) on this feature are proceeding well. Comments on their
30% submittal are currently being addressed. A finite element analysis has been initiated
and is being reflected in design efforts. Also, a task order with INCA is being developed
to provide design checks.
As-built Drawings A task order is being developed
with AIMSI Engineers to perform this work. The order has been negotiated and is nearing
award. A site visit will be scheduled soon as part of this effort.
EB Permanent Embankment The DM level design of this
feature is currently about 70% complete and will be finalized later this summer.
Stoplogs Efforts have been initiated to have the
Mobile District develop a design package and provide drawings for the stoplogs that they
have recently completed for their locks. Upon receipt of this package, it is planned to
issue a task order to INCA to perform an independent technical review and to ensure that
these stoplogs will be suitable for this project.
EP-D New IDTs - The first of the four new IDT
contracts was awarded to Harza Engineering the week of 1 June. The remaining three are
still not far behind.
Disposal/Contractor Laydown Areas
Vulcan Materials Disposal Site Activities necessary
to acquire the real estate rights for this 46-acre site located about ¾ mile from the
proposed lock on Hwy 453 have been initiated. These include:
Completion of an HTRW assessment.
A coordination meeting with Vulcan officials on 21 June. The
boundaries of the proposed site were finalized. A decision has not yet been made on
whether to acquire the property in fee or acquire a long-term easement.
A site survey will be initiated by a Corps contractor in July. A
draft scope of work for this survey is under review.
A task order is being developed for one of the new lock A/Es
to develop necessary designs for this disposal site. This includes access roads, storm
water and erosion control measures, volumetric determinations, staging arrangements, and
final site characteristics.
Wayne Rains of TVAs Realty Transactions Group will be
responsible for the appraisal and acquisition process. It is planned to complete the
appraisal this FY. Acquisition activities will be dependent on funding levels next FY.
Cofferdam DM
Downstream cofferdam Harza submitted their 30% report
on schedule. A 30% review meeting is scheduled for 15 July in Nashville. It is expected
that a decision will be made at this meeting on the selection of the preferred alternative
or at least the development of gameplan to make this decision. The minimal disruption to
the operation of the existing lock during construction of this cofferdam is a major design
goal.
Upstream cofferdam Efforts have been initiated on a
scope of work for a task order to one of the new lock A/Es on the structural design
of this feature. It is hoped that this order can be issued in early August. Much of the
geotechnical design of this cofferdam will be performed by LRN.
Independent Technical Review Because of the
complexity of the design, the interrelationship of the cofferdam features, its importance
to dam safety, and the number of design groups involved, it was decided by the design team
to form an independent technical review (ITR) team for the entire Cofferdam DM. Although
all design work on this project undergoes an ITR, this proposed team would provide for a
comprehensive review of various related elements. LRNs Structural Section is in
charge of putting together this team. It is hoped that it can be formed in the next month
and begin participating by reviewing design decisions.
Value Engineering Study The first value engineering
(VE) study on this project will concentrate on the downstream cofferdam. Ted Davidson is
putting together a team that will be examining Harzas 30% report and possibly
examine other alternative concepts. One alternative proposed by Gordon McClellan consists
of a float-in wall section of the permanent lock wall that would eliminate the need for a
portion of the downstream cofferdam. Ted is expecting to bring in one of the new lock
A/Es to help in this study.
Materials DM
Efforts on this work effort have been initiated by LRNEP-G.
Samples have been obtained from two quarries and three sand pits. Additional sand pits and
at least one more quarry will be sampled. Testing of the samples will be performed by the
Waterways Experiment Station (WES).
Hwy/RR
Quarterly Design Meetings The next quarterly design
meeting is scheduled for 16-17 August at the Lake Barkley Resource Managers office. The
Hwy-only meeting is scheduled for the afternoon of 16 August. The joint Hwy/RR meeting is
scheduled for the morning of 17 August and the RR-only meeting that afternoon.
Highway DM
DM Design Activities performed during the month by
American Consulting Engineers (ACE) include:
 |
Navigation Span
- Span increased from 500 to 505 due to location of EB
pier in relation to the proposed guidewall
|
- Studying haunched vs. constant depth for 3-span plate girder
alternate. Continuing study of truss alternatives.
|
- Initiated study of drilled shaft deep water foundations
6 vs. 8 diameter and plum vs. battered.
- Continued analysis of 304 vs. 152 viaduct spans
- Continued on generating computerized rendering of the site
- Completed preliminary design of middle wall maintenance bridge
- Completed and received approval from KTC on boring plan. Initiated
field staking.
- Submitted US 62 and KY 282 interchange operational characteristics
report.
- Submitted urban vs. rural roadway template study
- Initiated maintenance of traffic study and drainage design
- Finalized ramp 1 and ramp 2 alignments
Powerhouse Island Access Ramp ACE submitted a
preliminary folio on this design. A meeting is planned for 19 July at KY Dam to discuss
this design with appropriate Corps, TVA, and ACE staff.
Pedestrian Corridor Analysis ACE submitted their
feasibility study examining the alternatives that were agreed to in the 12 May meeting. A
meeting is scheduled for 19 May at Lake Barkley Resource Managers office with all
pertinent design team members in an effort to select the preferred alternative. A memo
describing these alternatives and the feasibility study has been distributed to all
prospective attendees.
Geotechnical design - A task order was awarded in June for
Fuller, Mossbarger, Scott and May to prepare the geotechnical reports necessary for the
Hwy DM. Geotechnical design - A task order was awarded in June for
Fuller, Mossbarger, Scott and May to prepare the geotechnical reports necessary for the
Hwy DM. Geotechnical design - A task order was awarded in June for
Fuller, Mossbarger, Scott and May to prepare the geotechnical reports necessary for the
Hwy DM. Geotechnical design - A task order was awarded in June for
Fuller, Mossbarger, Scott and May to prepare the geotechnical reports necessary for the
Hwy DM.
Coordination with the Kentucky Transportation Cabinet
A response to LRNs letter of 30 December 1998 from the KyTC that documents
their position on betterment sharing has not yet been received. LRN is continuing the
refinement of a first draft of a betterment sharing agreement with the KyTC. It will soon
be forwarded to TVA for review and then to the KyTC. A fast track review and coordination
process by all parties will be required to get this agreement signed by late summer. It is
important that this letter from KyTC that documents their cost sharing computations be
received as soon as possible to expedite the drafting of this agreement.
Railroad DM
Walker Cemetery Access Road Hanson Engineers has
submitted the 100% Plans and Specifications for this road. The construction contract
documents are currently being prepared by LRN. It is expected that this construction
contract will be awarded to an 8A contractor in August. A site visit to determine if
graves are located outside the cemeterys fenced boundaries along the proposed
roads alignment was made in June. No graves were found in this area.
RR Design In addition to the cemetery access road
and WB utilities, Hanson Engineers have performed the following activities over the last
month:
- Submitted report on the preliminary design of the truss span
- Continued the collection of information for MCACES cost estimates
- Completed the study of alternatives for the wye track alignment.
- Continued the Section 303 (formerly 4(f)) Statement
- Continued preliminary foundation design
- Initiated study of Vulcan haul road bridge alternative analysis
Modification No. 2 to Hanson Contract
A scope of
work and negotiations for this effort have been completed. Award of this Modification will
occur soon.
WB Utility Relocations Hanson has submitted the
design of the water and sewer lines at a 75% level. It is anticipated that this
construction contract will be awarded in late summer. Required coordination and
development of legal documents with the owners could impact this schedule.
Geotechnical Design Harza continues in their
geotechnical analyses for the EB retaining walls and wye track alignment. Another task
order is under development to Harza to complete geotechnical studies for P&S on the WB
embankment.
TVA Transmission Towers Relocation
Eight Upstream Towers (four on each bank) - Design efforts by
TVA engineers are proceeding, with foundation/footing designs scheduled for completion
soon. An order has been placed to acquire the structural steel for all eight towers. Due
to scheduling conflicts within TVA and concerns about the Economy Act, it is still not
known what forces will be used to drive the piles necessary for the tower foundations on
the powerhouse island. The Corps is now in the process of seeking approval by the
Assistant Secretary of the Army (Civil Works) to allow TVA to use members of its contract
partners in the construction of the towers. Due to the length of time this approval
process usually requires, it is not expected that significant efforts can be executed this
fiscal year for the towers on the powerhouse island. It is still planned to issue a
construction contract for the concrete footings for four towers on the east bank, possibly
late this summer. Eight Upstream Towers (four on each bank) - Design efforts by
TVA engineers are proceeding, with foundation/footing designs scheduled for completion
soon. An order has been placed to acquire the structural steel for all eight towers. Due
to scheduling conflicts within TVA and concerns about the Economy Act, it is still not
known what forces will be used to drive the piles necessary for the tower foundations on
the powerhouse island. The Corps is now in the process of seeking approval by the
Assistant Secretary of the Army (Civil Works) to allow TVA to use members of its contract
partners in the construction of the towers. Due to the length of time this approval
process usually requires, it is not expected that significant efforts can be executed this
fiscal year for the towers on the powerhouse island. It is still planned to issue a
construction contract for the concrete footings for four towers on the east bank, possibly
late this summer. Eight Upstream Towers (four on each bank) - Design efforts by
TVA engineers are proceeding, with foundation/footing designs scheduled for completion
soon. An order has been placed to acquire the structural steel for all eight towers. Due
to scheduling conflicts within TVA and concerns about the Economy Act, it is still not
known what forces will be used to drive the piles necessary for the tower foundations on
the powerhouse island. The Corps is now in the process of seeking approval by the
Assistant Secretary of the Army (Civil Works) to allow TVA to use members of its contract
partners in the construction of the towers. Due to the length of time this approval
process usually requires, it is not expected that significant efforts can be executed this
fiscal year for the towers on the powerhouse island. It is still planned to issue a
construction contract for the concrete footings for four towers on the east bank, possibly
late this summer. Eight Upstream Towers (four on each bank) - Design efforts by
TVA engineers are proceeding, with foundation/footing designs scheduled for completion
soon. An order has been placed to acquire the structural steel for all eight towers. Due
to scheduling conflicts within TVA and concerns about the Economy Act, it is still not
known what forces will be used to drive the piles necessary for the tower foundations on
the powerhouse island. The Corps is now in the process of seeking approval by the
Assistant Secretary of the Army (Civil Works) to allow TVA to use members of its contract
partners in the construction of the towers. Due to the length of time this approval
process usually requires, it is not expected that significant efforts can be executed this
fiscal year for the towers on the powerhouse island. It is still planned to issue a
construction contract for the concrete footings for four towers on the east bank, possibly
late this summer.
Three Downstream Towers (69 kV) - A decision on relocating
the three downstream towers is still pending based on a review of the engineering analysis
performed by Harza Engineers in their DM level design of the downstream guidewall. The
results of Harzas analysis were included in their 30% submittal of the D/S guidewall
DM and will be refined in their upcoming 70% submittal. A final decision on the fate of
these three towers will be made after a review of this report by LRN and TVA. Preliminary
indications are that the 3 towers will not have to be relocated.
Miscellaneous
CADD Standards/Drawing Title Blocks LRN and TVA have
agreed upon a drawing title block and standard sheet size to be used for this Project. Ron
Carter in EP-D is the point of contact on this issue.
Development of Drawing Library System LRN plans to
develop a library of all drawings that can be accessed by all members of the design team.
When it is complete, a message will be sent to all design team members and will be posted
on the Homepage.
KY Lock Telephone Directory
A list of all
organizations and key personnel involved in the design of this project that contains their
address, phone numbers and email addresses is available upon request to Don Getty, (615)
736-2346 [don.b.getty@usace.army.mil].
|