Revised 10 January 2000
PM Don Getty
A.
PROJECT
DESCRIPTION
Kentucky Lock is located in western Kentucky at Mile 22.4 of the
Tennessee River. A
feasibility report completed in 1992 recommended a new 110' x 1200' lock
adjacent and landward of the existing 110' x 600' lock.
The project was authorized for construction in WRDA 96 and
construction commenced in July 1998.
Based on an expected funding level of $25.2M (Appropriated $30M
minus Savings & Slippage), our FY 01 spending plan is provided below:
$ 4.5M
In-house design and management
$ 1.2M
Other Corps
$ 0.5M
TVA in-house
$ 7.5M
A/E Contract Design
$11.5M
Construction and Real Estate Acquisition.
B. GENERAL
Significant
activities, issues raised, and decisions made during the month on the
project include
:
·
Use
of Roller Compacted Concrete in Lock Walls
An analysis is currently underway to evaluate the use of roller
compacted concrete (RCC) versus cast-in-place concrete in the construction
of much of the new locks walls. Preliminary
design efforts by Harza Engineers two years ago had shown a substantial
cost savings by using RCC in lieu of cast-in-place, on the order of $10M.
However, several design changes, technical concerns, and
construction evaluations in the meantime have reduced, if not eliminated,
any potential savings from the use of RCC.
The ongoing analysis will determine up-to-date costs and examine
the pros and cons of using RCC. A
decision on whether or not to continue the pursuit of RCC is expected by
February.
Construction
activities:
·
TVA
Transmission Towers
Only limited efforts on the towers have occurred over the last month.
TVA crews are expected back on site in force in January in an
effort to have the first new line across the canal by the end of February
·
West
bank Hwy/RR Embankment
The unusually cold and wet weather over the past month has prevented
much activity on this contract. Construction
activities will resume as weather permits.
C. PROGRESS
FOR THE MONTH:
Environmental
·
Wetland
Mitigation
- TVA completed the acquisition of this 25 acre site near
Benton, KY on 3 January. Final
design efforts for establishing the wetland site are ongoing by Hanson
Engineers. A 50% P&S
submittal and review meeting is scheduled for 29 January.
·
Mussel
Mitigation
The mussel survey in Lake Barkley has commenced and preliminary
results were presented at the 5 December meeting in Vicksburg.
The Lake Barkley survey and Kentucky Lake surveys will resume this
spring as the weather permits.
·
Tailwater
Fishing Mitigation
After review of ACEs initial design drawings and after viewing
tests at the Navigation Model on 5 December, the following changes are
being implemented in the design of the fishing jetties and their
associated facilities:
·
The
two jetties will be oriented perpendicular to flow.
·
The
jetties will be moved downstream approximately 50 so as to not impact
the operation of the existing boat ramp.
·
The
top length of the upstream jetty should be shortened by 15 feet, for a top
length of 85 feet out from the 300 contour.
·
The
ADA compliant access ramp should be located on the downstream side of the
downstream jetty.
·
The
curb height on the lower-most ADA fishing platform should be 6 high.
·
A
flushing hydrant location should be shown.
·
The
possibility for adding stairs at the downstream end of the new parking lot
should be considered.
·
Draft
Supplemental Environmental Impact Statement The
in-house review for this document is scheduled for mid-January with a
public release in early February.
WES
Navigation Model
Status
- All of the proposed condition features have been installed and testing
for this second phase is ongoing. New
features in the model include the proposed 1200 lock, the piers for the
new bridges, the two fishing piers, the two fishing jetties, and removal
of the two mooring cells downstream of the powerhouse island.
Activities during the past month include:
·
Environmental
Coordination Meeting
This meeting was held on 5 December (minutes available).
The main purpose of the meeting was to view navigation and spillway
dike tests and discuss the results of measured post-project velocity
impacts to mussel bed areas. Significant discussions included:
·
It
was agreed to use the velocity data measured to date in the model in the
analyses to be presented in the Supplemental EIS.
·
All
underwater activities to be included in the Supplemental EIS were
identified and discussed as needed.
·
Language
to be included in the Corps construction specifications regarding
potential fish kills was clarified.
·
The
proposed mooring buoys downstream of the I-24 bridge are being dropped
from consideration in this project.
·
The
proposed spillway dikes were viewed in the model and discussed.
Currently, they are not part of the project but will be considered
for inclusion and they are to be included in the SEIS since they could be
constructed as a Federal feature in the near future.
From viewing flow patterns in the model, it appears that the
spillway dikes will reduce the likelihood of recreational craft to be
pulled into the dangerous spill zone and may affect fishing patterns in
the tailwater.
·
Railroad
Truss Float-in Meeting
A meeting to view the RR truss float-in tests and PH Island pier
impact tests was held on 6 December.
The tests have been held to determine the method and impacts to
float this truss from the west bank boat basin across the river to its
final resting position on the east bank.
Significant results from the meeting/viewing include:
·
The
tests verified the need to remove the West KY Rural Electric Cooperative
transmission line crossing the TN River immediately downstream of the boat
basin.
·
A
piling in the boat basin appeared more effective than lines to shore in
controlling the truss assembly as it leaves the boat basin.
·
It
was agreed to model test the use of a third tug during the transport.
·
The
format and type of information to provide to prospective bidders was
agreed upon.
·
The
results of the pier impact tests show that impacts are very unlikely and
the resulting forces would be low as compared to other design forces.
·
Model
schedule and priorities
The anticipated sequence of upcoming major activities is provided
below:
·
Install
downstream cofferdam
Tests will be performed to determine impacts and to potentially lessen
the impacts to navigation use of the existing lock both during
construction of the cofferdam and after its construction is completed.
·
Future
meetings:
·
Navigation
A
meeting with the navigation industry to view conditions with the
downstream cofferdam in place and under construction is planned after
testing is substantially complete. This
meeting is still tentatively planned for the late February/early March
timeframe.
WES
Lock Model
Testing efforts are complete and the draft final
report is being circulated for review comments. Potential changes to the design of the upstream guardwall and
upstream topography could cause this model to be reactivated to ensure
that any changes do not adversely impact the design of the new locks
intake system.
Lock
Design
In-house.
The main focus of in-house resources is to manage both A/E and
construction contracts needed for critical path items.
Work in support of the Upstream Cofferdam and Excavation Contract
is ongoing. Major features
included are, Upstream Cofferdam design A/E administration, Upstream
excavation design, Vulcan Haul Road & Disposal Area A/E
administration, Anchoring existing lock wall design, Instrumentation of
Existing Lock Wall design, and Area Drainage design.
Work is also continuing on the geotechnical drilling program, the
support of WESs Navigation Model work, new lock stability, existing
lock lower land wall stability, miter gate design, lock intake trashrack
design, the Materials DM, and the east bank permanent embankment.
Electrical/Mechanical
Design.
A comment resolution meeting for the 75% DM submittal was held on
16 November (Minutes Available). The
95% submittal is expected in mid January.
Upper Approach
Walls
The geophysical survey of
the middle wall nose pier area has resulted in recommendations for
changing the location for the nose pier area.
This and other issues will be discussed at the 60% DM review
meeting on 5-8 February.
Miter
Gate Design. Louisville
District is continuing work on the Plans & Specifications for this
feature.
As-built
Drawings
A preliminary submission of the final folio is expected on 11 January.
The final folios will contain AIMSI, TVA and Corps drawings and
this will complete AIMSIs efforts on this task.
Site Utilities
The 35% submittal for this effort from Harza is expected in January.
Site Seismic
Criteria
Harza Engineers are continuing in their efforts on this report.
Upstream
Monolith Design The task order for Black & Veatch prepare plans and specifications
for construction of the upstream gate and valve monoliths has been
negotiated and should be awarded this month.
B&Vs scope includes requirements for a Phase II thermal
analysis.
Lock RCC Design
The draft scope for Harza to design the lock roller compacted concrete
(RCC) is essentially
complete. However, this
effort has been put on hold until a decision is rendered on the
cost/feasibility of using RCC in the lock walls (See Significant
Activities on page 1).
Demolition and
Modification of Existing Operations Building
The
pile founded portions of the existing lock operations building will have
to demolished once excavation in that area occurs.
These portions, a shop area and public restroom entrance, were
additions to the original structure.
Since the KY Dam Project is on the National Register of Historic
Places, the building will be restored as close as practical to its
original condition. A task
order with Harza has been issued and they will prepare plans and
specifications for these changes.
New Operations
Building
The 90% DM submittal for this facility was received from Harza in January
and review is currently underway.
Transmission
Towers
Construction
progress
See
Construction Activities in Section B.
Retaining wall
for three downstream, east bank 69 kV towers The
60% DDR for P&S by Harza was submitted in November.
Its design is being coordinated with the design of the downstream
cofferdam a main topic of the 10 January meeting in Chicago.
The construction of this wall will be included in the bridge pier
construction contract planned for advertisement this spring.
Disposal/Contractor
Laydown Areas
Vulcan
Materials Disposal Site The review of B/Gs 95% plans & specification submittal for
the Vulcan Haul Road is complete and B/G is working on the 100% package,
scheduled for submission in late January.
The Vulcan Haul Road and Disposal Area construction will be
included with the Upstream Cofferdam and Excavation construction contract
we plan to advertise this spring. An
in-house Value Engineering Study of this design will commence this month.
Activities necessary to acquire the 15-year easement from Vulcan
Materials for this 43-acre site located about Ύ mile from the proposed
lock on Hwy 453 are ongoing.
Construction
Laydown and Scheduling Task Order - A
review meeting of B/Gs 90% submittal was held on 13 December at Barkley
(minutes available). All
significant comments were discussed and resolved.
A final submittal is expected in April upon completion of Harzas
site utilities efforts.
Cofferdam
Design
Downstream
cofferdam
The 60% DDR submittal by
B/G was received in early January. A
trip to WES with navigation industry representatives to view the
navigation model with the downstream cofferdam in place is tentatively
scheduled for late February/early March.
Upstream
cofferdam
Black & Veatch submitted the 95% complete
Plans & Specifications for this feature in December.
A review comment and resolution meeting is scheduled for 18
January.
East Bank
Temporary Cut-off Analysis The 70% submittal for
this analysis was received in November and has been reviewed.
A comment resolution meeting is scheduled for 19 January.
Sheetpile
Acquisition
Olmsted is currently pulling piles and loading them on barges for the
new McAlpine Lock project. It
will be in the March time frame before piling is available for our
project. This month, the
Corps Operations Division plans to initiate dredging for barge access
for delivery of the sheetpile to the Taylor Park Campground site.
It is now planned to contract for the actual transport of the
sheetpile from Olmsted to KY Lock. We
will continue to coordinate with the Olmsted Resident Engineer on
logistics for this transfer.
Materials
DM
The ITR comment resolution meeting for the 60%
product was held on 4 December. The
DM is scheduled to be complete at the start of FY02. If it is decided to pursue RCC lock walls, we will work with
WES to determine tests required for lock chamber RCC design.
Close coordination will be required on scheduling these tests so
results are available for RCC design task order input.
Relocations
·
RR/Hwy
Design
·
TN
River Bridges Substructure P&S
The 50% drawings for this contract were mailed for review late the
week of 1 January. In
addition to the piers and abutments for the RR and Hwy bridge, this
contract will include the construction of the temporary retaining wall for
the three downstream 69 kV transmission towers and the pre-excavation
required for the downstream guidewall.
A 50% review meeting is scheduled for 30 January.
·
East
bank approaches P&S
The
scope for ACE to do this work is nearing completion.
An underwater surveying task has recently been added to ACEs
scope to better define top of rock for the pre-excavation in the vicinity
of the east bank piers. Scoping
efforts for HEI on this work have been initiated.
This design work as well as ongoing construction on the west bank
will be the topic of discussion at the 29 January meeting on site.
·
Utility
Relocations
Several site visits and meetings with local utilities are planned over
the next month to discuss proposed relocations and construction impacts.
These include:
·
W.
KY RECC
Proposed work include elimination of their TN River crossing with
attendant connection to station power on east bank.
Also, phased relocations on the east bank during different
construction phases and re-connection to remote TVA tower lighting near
I-24 will be discussed. A
relocations contract is currently under development.
·
Kentucky
Utilities
We will discuss proposed fill and riprap placement at a KU tower on
the west bank, possible line outage during RR truss float-in process, and
current design of Vulcan Disposal Area.
·
Jackson
Purchase Energy Corp.
Will discuss impacts and possible modifications to lines in Vulcan
Disposal Area.
·
City
of Grand Rivers
Will discuss relocation of 8 water line on east bank.
Miscellaneous
KY Lock
Telephone Directory A list of all organizations and key personnel involved in the
design of this project that contains their address, phone numbers and
email addresses is available upon request to Don Getty, (615) 736-2346 [don.b.getty@lrn02.usace.army.mil].
Future
Project Meetings
·
10
Jan D/S cofferdam Elec/Mech coordination and tower retaining wall
coordination in Chicago
·
11
Jan Disposal area/haul road Value Engineering (VE) team kick-off meeting
·
17
Jan Kickoff for U/S monolith design in KC
·
18
Jan 95% U/S Cofferdam in KC
·
18
Jan VE team site visit
·
19
Jan 70% review EB Temporary Cutoff in KC
·
29
Jan Hwy/RR Roadways/Approaches Tri-annual meeting at site
·
29
Jan Wetlands 50% P&S review meeting at site
·
30
Jan - Hwy/RR TN River Bridges
Substructures 50% P&S Review meeting at site
·
31
Jan D/S cofferdam at site
·
Jan/Feb
W. KY RECC at site
·
Jan/Feb
Jackson Purchase Energy Corp. at site
·
Jan/Feb
KU at site
·
Jan/Feb
City of Grand Rivers at site
·
5-8
Feb 60% U/S Approach Walls in Seattle
·
Feb/March
WES Downstream Cofferdam Nav. Model Demonstration
·
February
Olmsted Sheetpile Logistics Coordination at Olmsted
End of Report
|