Revised 7 August 2001
PM Don Getty
A. PROJECT DESCRIPTION
Kentucky
Lock is located in western Kentucky at Mile 22.4 of the Tennessee River. A feasibility report completed in 1992 recommended a new 110'
x 1200' lock adjacent and landward of the existing 110' x 600' lock.
The project was authorized for construction in WRDA 96 and
construction commenced in July 1998. Based on an expected funding level of $25.2M (Appropriated
$30M minus Savings & Slippage), our FY 01 spending plan is provided
below:
$ 4.5M
In-house design and management
$ 1.2M
Other Corps
$ 0.5M
TVA in-house
$ 7.5M
A/E Contract Design
$11.5M
Construction and Real Estate Acquisition.
B. GENERAL
Significant
activities, issues raised, and decisions made during the month on the
project include
:
·
FY
02 Funding Outlook –
The status of KY Lock’s fiscal year ’02 funding is shown below:
Stated Capability
$55.0M
President’s Budget
$14.4M
House Appropriations
Sub-committee
$20.4M
Senate Appropriations
Sub-committee
$23.0M
Conference Committee
? (September)
Since the Project’s
critical path funding needs are in the neighborhood of $40 to $45M, the
range of the above funding amounts will have an impact on the pace of the
project. We will continue with
both construction and design efforts next year, but at a reduced level.
·
Upcoming
Construction Contracts – Even with the anticipated FY 02 funding levels,
we are planning to award three of the four construction contracts reported
last month. Due to the FY02
funding outlook, we have cancelled the Construction Field Office
solicitation. The Upstream
Cofferdam was advertised on July 2nd with a bid opening
scheduled for August 21st. A
pre-bid meeting at the site for potential bidders was held on July 25th.
There will be one amendment to this solicitation that may delay the
bid opening by a few days. The
Bridge Piers were advertised July 5th and a pre-bid meeting was held on
July 26th. An amendment was
issued on 31 July with another one planned before the 23 August bid
opening. The Wetlands at Benton are planned to be a negotiated
contract that should be issued in the September timeframe.
·
Final
Supplemental Environmental Impact Statement and Record of Decision
– No public comments were received during the comment period on the Final
SEIS and BG Hawkins signed the Record of Decision (ROD) on 20 July.
The ROD summarizes all agency comments on the FSEIS and documents
the Corps’ plans to proceed with all of the proposed changes to the
Project since the original 1992 EIS. Project features that are immediately impacted by the ROD
include the addition of the expansion of the west bank boat basin to the
Bridge Pier solicitation and the start of the mussel relocation efforts
under the proposed west bank fishing jetties.
·
FY
01 Reprogramming Action
– Higher authorities in the Corps have directed Nashville District to
allow reprogramming of $1M in FY 01 funds to be used by another navigation
project, Olmsted L&D. We
have planned for this reduction in funding and it will not significantly
affect progress on the KY Lock project.
Most of the reduction will be accommodated by reducing the FY 01
funds obligated for the two large construction contracts under
advertisement. Since the
advertisement of the contracts were delayed over original plans, they did
not require significant funding in this FY.
Construction
activities:
·
TVA
Transmission Towers
– The fourth and final tower on the east bank was completed in
July. Erection work for the
fourth and final tower on the powerhouse island is scheduled to commence
the week of 13 August. TVA
still plans to complete this tower and all other relocation efforts by the
end of September. TVA’s Heavy Equipment Division has initiated the
construction of a $1.1M retaining wall to protect the three downstream 69
kV transmission towers. The
first shipment of Z-piles for the wall is expected to arrive the week of 13
August. This wall’s
construction is scheduled to last until December 2001.
·
West
Bank Hwy/RR Embankment
– Murray Paving continued construction of the combined embankment located
to the east of the existing railroad embankment in July.
Limited work also occurred to the west of the existing railroad
embankment in preparation for the placement of the lightweight fill that
should commence by the second week in August.
This $5.9M contract is approximately 30% complete.
C. PROGRESS FOR THE MONTH:
Environmental
·
Supplemental
Environmental Impact Statement – See Significant
Activities under B.
·
Wetland
Mitigation
- Coordination with the Small Business Administration for this
construction solicitation has been completed and contract negotiations with
an 8A firm are expected to commence within the next 1.5 months.
·
Mussel
Mitigation
– All underwater survey work has been completed and
report compilation is ongoing.
·
Tailwater
Fishing Mitigation
(West Bank Jetties) – The full-scale mussel relocation efforts
within the proposed jetties’ footprints are to commence on 6 Aug and will
take 5 to 7 weeks to complete. The
jetties design quantities are being refined by a hydrographic survey the
week of 6 August and contract plans are on hold until this survey can be
compiled. The construction of the jetties is still anticipated to
commence by late summer
WES
Navigation Model
Status
– A draft final report is currently under review.
WES
Lock Model
Jose’ Sanchez from WES came to Nashville this month
to brief the design team on test results with the new middle wall nose pier
location. The testing did
indicate stronger vortices forming than the previous location, but they
only occur during extreme headwater and tailwater conditions and they can
be mitigated with a slower valve time.
Therefore, the testing confirmed the new nose pier location is
acceptable. Jose indicated he
will decide whether to recommend further testing to analyze other possible
mitigation measures when he issues his report.
Lock
Design
In-house.
The main focus of in-house resources is to manage A/E
contracts and initiate the new construction contracts mentioned in section
B above. Work is continuing
on, the support of WES’s Lock Model work, existing lock anchoring and
instrumentation design, miter gate design, and the Materials DM.
Electrical/Mechanical
Design.
MWH has received the 95% submittal comments and are working on
resolving for a final submission before the end of the FY.
Upper Approach
Walls
– The final submittal for
this task order is being printed by INCA and will be submitted to the
District later this month.
Miter
Gate Design. Louisville
District’s work on the Plans & Specifications was delayed for other
in-house work. They are still
preparing to send INCA a package to perform an engineer’s check.
Plans & Specs will be complete and ready for ITR review by
mid-September.
Site Utilities
– The 70% submittal is being assembled by MWH and is expected in the
District the week of 6 August.
Upstream
Monolith Design – Black & Veatch is working on tasks associated with the recently
awarded task order modification which addresses seismic stability analysis.
The 30% submittal was delayed approximately 60 days due to the
requirement for this work.
Downstream Lock
Design
- A coordination meeting with
LRH and Bergmann/Gerwick to discuss issues common to the downstream
cofferdam and downstream lock structure designs was held in Nashville on
August 1st. Issues
discussed included drilling of additional exploratory holes and anchoring
of float-in segments to cast in place wall monoliths and thermal
considerations of the anchoring. Also
discussed was available and needed construction clearances.
Demolition and
Modification of Existing Operations Building –
District
review comments on the 95% submittal of Plans & Specifications were sent to MWH the
first part of August. This
design will be complete later this summer.
New Operations
Building & Maintenance Complex –
MWH was
awarded this task order in July and have begun work on the designs.
A 60% submittal is expected the first part of October.
East Bank Roadways/Site Plan P&S
– Efforts have been initiated to issue a modification to ACE to prepare
P&S for the parking lots, roadways, and site grading for the east bank
area of the lock.
Transmission
Towers
Construction
progress –
See
Construction Activities in Section B.
Disposal/Contractor
Laydown Areas
Vulcan
Materials Disposal Site – This task order was completed in July.
Cofferdam
Design
Downstream
cofferdam
– Award of this task order
is expected the first part of August.
Bergmann/Gerwick attended the meeting discussed in “Downstream
Lock Design” above to discuss issues related to LRH’s work.
At this meeting a simple and inexpensive method to allow alignment
of permanent wall monolith joints with joints in the float-in sections of
the cofferdam was agreed to.
Materials
DM
WES is continuing testing on concrete mixes.
We are still on schedule to issue an essentially complete report at
the beginning of FY 02. Reports
on some testing continuing past this date will be issued as an addendum to
the report.
A meeting with potential aggregate suppliers was held
on 27 July at the Barkley Resource Managers Office.
The purpose of the meeting was to discuss aggregate specifications
for the two advertised construction contracts, anticipated specifications
for lock construction, and testing results to date.
Minutes for this meeting will be available by mid-August on the
Kentucky Lock web site.
Relocations
·
RR/Hwy
Design
·
Substructure Solicitation – The team prepared one amendment for the
solicitation in July and is working on a second one based on questions that
were asked in the pre-bid meeting on 26 July.
The first amendment included the addition of plans and
specifications for the expansion of the west bank boat basin.
·
East Bank Approaches – A design coordination meeting was held on 26
July to discuss primarily the 50% East Bank P&S submittals by ACE and
Hanson. All issues were
resolved and both firms are proceeding with the development of a 90%
package for submittal by September 28, 2001.
·
West Bank Embankment Modification – Hanson submitted the final P&S for
the extension of the railroad embankment and water line relocation on the
west bank. This work will be
accomplished through a modification to Murray Paving that should be
executed this FY. The water
line relocation has been submitted to the KY Division of Water for
review/approval.
·
Superstructure Design – Scoping efforts are ongoing with both Hanson and
ACE to commence the final design of the bridges’ superstructure and all
remaining facets of the Hwy and RR relocations.
Miscellaneous
KY Lock
Telephone Directory – A list of all organizations and key personnel involved in the
design of this project that contains their address, phone numbers and email
addresses is available upon request to Don Getty, (615) 736-2346 [don.b.getty@lrn02.usace.army.mil].
Future
Project Meetings
·
August
9 – Follow-up meeting with Rogers Group Quarry
·
Sept
26-27 (Tentative) – 70% Site Utilities at KY Lock
·
October
25 – 90% East Bank Approaches Meeting
End
of Report
|