|
































|
Revised 10 Aug 1999
PM Don Getty
A. PROJECT DESCRIPTION
Kentucky Lock is located in western Kentucky at Mile 22.4 of the Tennessee River. A feasibility report completed in 1992 recommended a new 110' x 1200' lock adjacent and landward of the existing 110' x 600' lock.
The project was authorized for construction in WRDA 96. FY 98 funding of $4M was used to continue WES model studies, the Lock DM, Transmission Tower
DM, subsurface exploration, and initiate the Railroad DM. Construction on the project was initiated with the construction of an access road on the
powerhouse island that was completed in August 1998. Due to fiscal reprogramming efforts within the Corps, the FY 99 funding plan of $12.6M is:
$3.3M - Lock DM
$2.7M - Railroad DM
$1.9M - Highway DM
$0.7M - Cofferdam DM
$0.16M - Materials DM
$2.2M - Transmission Tower Relocation
$0.6M - Lock and Navigation Models at WES
$0.2M - Environmental Studies
$0.4M - Construction Contracts
$0.44M - Management/Miscellaneous.
Subsurface exploration costs are included in the costs for the DM's above.
B. GENERAL
Homepage - Additions/improvements to KY Lock's Homepage, www.orn.usace.army.mil/poa/kylock, continued over the last month. Notable
additions include updated pictures of the navigation model and progress reports and a partial listing of the design team.
FY 00 Funding Outlook - Here is what is known about KY Lock's funding levels for FY 00:
President's Budget Submission $7.75M
Senate Appropriations Sub-Committee $9.75M
House Appropriations Sub-Committee $15M
House/Senate Conference Committee ? (probably in September)
Stated capability of Project $15M
The stated capability of the project is the funding level required to keep the project's completion date as early as possible.
C. PROGRESS FOR THE MONTH:
Environmental Highway Environmental Assessment - The biological assessment was mailed to the US Fish and Wildlife Service on 4 August. This schedule
should allow for the preparation and completion of an Environmental Assessment prior to the advertisement for the construction of the West Bank
RR/Hwy embankment early next winter.
Environmental Coordination -A meeting at WES (Vicksburg) to
view existing conditions in the navigation model is scheduled for the
morning of 19 August. Representatives of the KY Dept. of Fish and Wildlife and the US F&W are expected to attend along with Corps and TVA personnel.
Cultural Resources Assessment - A task order was issued last
month to Duvall and Associates to complete the remaining cultural and
historical surveys and compliance tasks. Data gathering for this effort has been initiated and a coordination meeting with the Kentucky State Historic
Preservation Officer is scheduled for 19 August at KY Lock.
Exploration - The Nashville District's Drill Crew has completed 9 of the
28 holes to be drilled on the east bank (EB) Hwy 62 alignment. This week they started on the 11 holes scheduled to be drilled for the Hwy 62 bridge
over the P&L RR.
The Vicksburg District's Drill Crew completed all 28 holes
planned to be drilled along the Hwy 62 alignment on the WB.
Overwater drilling was schedule to commence by Harza/H.C.
Nutting on 10 August. Included in this task order was drilling for: 1) Hwy
bridge piers, 2) D/S cofferdam, 3) U/S approach walls' drilled shafts, 4)
possible downstream bent locations for truss assembly and 5) RR bridge piers
4 and 14 and commensurate Hwy bridge piers (probably via land bridge).
Testing - A task order has been initiated for FMSM to
perform all the geotechnical testing for the remainder of the drilled
samples.
WES Navigation Model
After solving several chronic water supply problems related
to some old equipment on the model, calibration testing commenced the week
of 6 July. Existing condition testing for the five flow/tailwater elevation
combinations selected is currently underway and scheduled for completion the
week of 16 August. Correspondingly, two meetings have been scheduled for
that week to view the model, review the existing condition results, and
discuss future tests. The first meeting on 19 August will concentrate on environmental interests. The second meeting on 20 August will involve
navigation interests. Of particular interest from an environmental
standpoint is the effect the project and the dam's operation will have on
the extensive mussel population downstream. Acoustic doppler equipment is
being used to measure pre and post condition velocities in an attempt to
quantify the effects on the mussel habitat.
WES Lock Model
LRN sent the final upstream topography to WES in early July
for incorporation into the Lock Model. Testing of this new topography and
the upstream floating guardwall are the last planned tests for this model.
The tests are anticipated for this fall.
Lock Design
In-house efforts continue to focus on the support of WES's
Lock and Navigation Model work, new lock stability, miter gate design,
culvert valve design, preliminary electrical/mechanical design, east bank
permanent embankment, and the development and managing of task orders.
Electrical/Mechanical Design. A new task order to take the
electrical/mechanical designs to a DM level has been awarded to Harza. A
10% progress meeting was held at the site on 20 July with maintenance
personnel in attendance. A 20% report has been received and is currently
under review. A 20% conference call is scheduled for 18 August. As part of
the corrosion mitigation design efforts, TVA will be initiating a program to
collect and analyze lake water samples.
Site Development - John Manor of LRN has completed
conceptual designs and drawings of the new lock's site development
(available upon request). A task order is being developed with Gresham
Smith and Partners to take this conceptual design to a DM level design. A
scope has been finalized and estimates have been prepared. Negotiations are
scheduled for 12 August. Delays in developing this task order are causing
the postponement of a planned meeting at the KY Fish and Wildlife
Department's visitor center in Frankfort, KY for the purpose of exploring
partnering possibilities for KY Lock's possible visitor center. Avis
Kennedy of LRNCO-T is continuing in her efforts to obtain guidance from
higher Corps authority on whether and how the visitor center can be included
as part of the project.
Lower Guidewall - Harza submitted their 70% design report
the week of 2 August and it is currently under review. A 70% review meeting
is tentatively scheduled for the week of 23 August in Chicago.
Upper Approach Walls - A task order to advance the upstream
guardwall to DM level has been scoped and negotiations are planned with INCA
Engineers. This task order should be awarded this month. Floating Caisson- A 70% submittal on this DM level effort
was made in July and review comments were returned to INCA on 23 July. This
new caisson will provide for 1.5' more damming height than the existing
caisson (for a total height of 29.5'). The new caisson will also be able to
be set in 14' of water, 1' less than the existing caisson. The dewatering
pumps and required piping will be permanently attached to the caisson,
resulting in a faster and more efficient chamber dewatering.
Miter Gate Design - LRL has completed the initial
construction of finite element model for the gates and analyses with it are
ongoing. Design efforts are proceeding on track for a 75% submission by the
end of August. Efforts are still underway to issue a task order to INCA to
provide design checks.
As-built Drawings - A task order was issued to AIMSI
Engineers to perform this work. Data gathering efforts are underway with
completed site visits to KY Lock, TVA offices, and the Old Hickory
Electrical Service Section.
EB Permanent Embankment - The DM level design of this
feature is currently about 70% complete and will be finalized later this
summer.
Stoplogs - Efforts to have the Mobile District develop a
design package for their existing stoplog design have been cancelled due to
the inability of LRN's existing derrick boats to accommodate the stoplogs'
weight. LRN now plans to design shorter and lower weight stoplogs in-house.
Project Utilities - Members of the LRN design team have
initiated efforts to identify design responsibilities for all of the known
utility relocations and modifications associated with this project. A draft
memo of these responsibilities is currently under review.
EP-D New IDT's - Contracts have now been awarded to three
of the four new lock A/E's. INCA and a joint venture of Bergmann Associates
and Ben C. Gerwick, Inc. are the latest awards. The last A/E contract is
expected to be awarded any day now.
Disposal/Contractor Laydown Areas
Vulcan Materials Disposal Site - Activities necessary to
acquire the real estate rights for this 46-acre site located about 3/4 mile
from the proposed lock on Hwy 453 have been initiated. These include:
* A task order has been scoped and will be awarded soon to Bergmann
Associates/Ben C. Gerwick (BA/BCG) to develop necessary designs for this
disposal site. This includes access roads, storm water and erosion control
measures, volumetric determinations, staging arrangements, assessment of
impacted utilities, and final site characteristics.
* A coordination meeting with Vulcan officials, TVA real estate
personnel, and design representatives of BA/BCG was held at the site on 4
August (minutes are available). Planned design features and the real estate
acquisition process were discussed. A significant remaining issue is the
determination of whether the site will be acquired in fee or if a long term
easement will be obtained. Discussions between TVA and the Corps are
planned over the next few weeks in an attempt to make this decision.
* A site and boundary survey was initiated by Amercan Engineers the
week if 9 August.
* TVA will be responsible for the appraisal and acquisition process.
The appraisal will not begin until the site survey is complete. If a long
term easement is chosen, then the appraisal will commence after preliminary
designs by BA/BCG are complete. If sufficient funding is received, it is
expected that this acquisition process will occur next fiscal year.
Cofferdam DM
Downstream cofferdam - A 30% review meeting was held on 15
July in Nashville (minutes available). A decision was made to proceed with
the design of the alternative expected to have the least impact on the
operation of the existing lock. However, it was recognized that significant
technical hurdles remained for this alternative before the design team could
accept its design. This alternative moves the cofferdam about 20' farther
away from the navigation channel than the other alternatives by
incorporating the cofferdam permanently into the new lock's gravity wall.
Upstream cofferdam - Scoping efforts are nearing completion
for a task order to one of the new lock A/E's on the structural design of
this feature. It is hoped that this order can be issued in August.
Independent Technical Review - Efforts are still underway
by LRN's Structural Section and Geotechnical Branch to assemble this review
team. It is hoped that it can be formed in the next month and begin
participating by reviewing design decisions.
Value Engineering Study - The first value engineering (VE)
study on this project will concentrate on the downstream cofferdam. Three
team meetings and a site visit have been held to date. The last meeting on
4 August involved representatives of BA/BCG who will be serving on the team.
A task order is being developed for BA/BCG to provide the technical designs
for at least two alternative concepts to those presented in Harza's 30% D/S
Cofferdam report. BA/BCG will be examining both a float-in wall/cofferdam
section and a full-width, braced cofferdam that will have a precast interior
wall panel.
Materials DM
Testing of the sand and rock samples delivered to the
Waterways Experiment Station (WES) are ongoing and completion is expected in
October. Future tests of cement and other materials are planned for next
FY.
Hwy/RR
Quarterly Design Meetings - The next quarterly design
meeting is scheduled for 16-17 August at the Lake Barkley Resource Managers
office (agendas available). The Hwy-only meeting is scheduled for the
afternoon of 16 August. The joint Hwy/RR meeting is scheduled for the
morning of 17 August and the RR-only meeting that afternoon.
Highway DM
DM Design - Activities performed during the month by
American Consulting Engineers (ACE) include:
- Navigation Span
- Develop two conceptual configurations for proposed truss and piers.
- Continued layout/design of 3-span plate girder alternate.
Alternative counterbalance design eliminates spiral geometry from bridge.
- Completed study of drilled shaft deep water foundations - 6' vs. 8'
diameter and plum vs. battered - for 304' spans. Design for 152' spans
continues.
- Developed barge impact forces for Powerhouse Island pier. Pier to
be designed to withstand impact without protection.
- 304' span design calls for 11' deep girders on 13'-1.5" spacing.
- Continued on generating computerized rendering of the site
- Completed preliminary design of east bank connector, west bank
connector, and TVA towers access road.
- Completed preliminary US 62/641 and 282 interchange ramp details.
- Completed Hwy capacity analysis for relocated US 62.
- Completed preliminary maintenance of traffic study.
Powerhouse Island Access Ramp - ACE submitted a preliminary
folio on this design and a meeting was held on 19 July at the site to
discuss it with appropriate Corps, TVA, and ACE staff (minutes available).
After discussing design criteria and TVA access needs, it was agreed to have
ACE develop alternate alignments to the one developed to date. These
alternate alignments may be presented at the 16 August meeting.
Pedestrian Corridor Analysis - After distribution of ACE's
feasibility study that examined alternate alignments for this corridor, a
meeting was held on 19 August at the site with all pertinent design team
members (minutes available). A preferred alternative alignment was
selected, the high, direct bridge over the locks. An unresolved issue was
the alignment of the corridor on top of the dam. ACE has been tasked to
examine three alternatives in this regard: two with the corridor on the
upstream side of the dam and one with the corridor on the to-be-abandoned RR
alignment on the downstream side. These alignments will be discussed at the
quarterly meeting on 16 August.
Middle Wall Maintenance Bridge - ACE is examining several
different span arrangements and centerline alignments for this bridge due to
stability concerns of the lock monoliths, physical constraints, and due to
concerns over the ability to place the chamber stoplog bulkhead. These
alternatives will be discussed at the 16 August meeting. This is a critical
issue considering the interrelationship of this bridge, the pedestrian/bike
bridge, and the powerhouse access ramp.
Geotechnical design - A task order was awarded in June for
Fuller, Mossbarger, Scott and May to prepare the geotechnical reports
necessary for the Hwy DM.
Coordination with the Kentucky Transportation Cabinet - A
response to LRN's letter of 30 December 1998 from the KyTC that documents
their position on betterment sharing has not yet been received. LRN is
continuing the refinement of a first draft of a betterment sharing agreement
with the KyTC. It will soon be forwarded to TVA for review and then to the KyTC. A fast track review and coordination process by all parties will be
required to get this agreement signed by late summer. It is important that
this letter from KyTC that documents their cost sharing computations be
received as soon as possible to expedite the drafting of this agreement.
Railroad DM
Walker Cemetery Access Road - Hanson Engineers has
submitted the 100% Plans and Specifications for this road. The construction
contract documents are currently being prepared by LRN. It is expected that
this construction contract will be awarded to an 8A contractor in September.
RR Design - In addition to the cemetery access road and WB
utilities, Hanson Engineers have performed the following activities over the
last month:
* Continued preliminary design of the truss span
* Initiated study of the modification of the RR bridge over KY 282
* Continued the collection of information for MCACES cost estimates
* Continued the Section 303 (formerly 4(f)) Statement
* Continued preliminary foundation design for approach spans
* Submitted preliminary study of Vulcan haul road bridge alternative
analysis
* Submitted preliminary concepts for EB Powerline Access Road
WB Utility Relocations - Hanson has submitted the design of
the water and sewer lines at a 75% level. It is anticipated that this
construction contract will be awarded in late summer. Required coordination
and development of legal documents with the owners could impact this
schedule.
Geotechnical Design - Harza submitted their 30%
geotechnical report for the analyses for the EB retaining walls and wye
track alignment the week of 2 August. A task order will be issued to Harza
the week of 9 August to complete geotechnical studies for P&S on the WB
embankment.
TVA Transmission Towers Relocation
Eight Upstream Towers (four on each bank) - Design efforts
by TVA engineers are proceeding, with foundation/footing designs scheduled
for completion soon. An order has been placed to acquire the structural
steel for all eight towers. Due to scheduling conflicts within TVA and
concerns about the Economy Act, it is still not known what forces will be
used to drive the piles necessary for the tower foundations on the
powerhouse island. The Corps is now in the process of seeking approval by
the Assistant Secretary of the Army (Civil Works) to allow TVA to use
members of its contract partners in the construction of the towers. Due to
the length of time this approval process usually requires, it is not
expected that significant efforts can be executed this fiscal year for the
towers on the powerhouse island. It is still planned to issue a
construction contract for the concrete footings for four towers on the east
bank, possibly early this fall. A scoping meeting to discuss the
construction sequencing of the towers is scheduled for 23 August in Chatanooga.
Three Downstream Towers (69 kV) - A decision on relocating
the three downstream towers is still pending based on a review of the
engineering analysis performed by Harza Engineers in their DM level design
of the downstream guidewall. The results of Harza's analysis were included
in their 30% submittal of the D/S guidewall DM and has been refined in 70%
submittal. A final decision on the fate of these three towers will be made
after a review of this report by LRN and TVA. Preliminary indications are
that the 3 towers will not have to be relocated.
Miscellaneous
Development of Drawing Library System - LRN plans to develop
a library of all drawings that can be accessed by all members of the design
team. When it is complete, a message will be sent to all design team
members and will be posted on the Homepage.
KY Lock Telephone Directory - A list of all organizations
and key personnel involved in the design of this project that contains their
address, phone numbers and email addresses is available upon request to Don
Getty, (615) 736-2346 don.b.getty@usace.army.mil
.
End of Report |