|
Revised 5 April 1999
Project Manager Don Getty
A. PROJECT DESCRIPTION
Kentucky Lock is located in western Kentucky at Mile 22.4 of the Tennessee River. A
feasibility report completed in 1992 recommended a new 110' x 1200' lock adjacent and
landward of the existing 110' x 600' lock. The project was authorized for construction in
WRDA 96. FY 98 funding of $4M was used to continue WES model studies, the Lock DM,
Transmission Tower DM, subsurface exploration, and initiate the Railroad DM. Construction
on the project was initiated with the construction of an access road on the powerhouse
island that was completed in August 1998. Due to fiscal reprogramming efforts within the
Corps, the FY 99 funding plan of $12.6M is:
$3.3M Lock DM
$2.7M Railroad DM
$1.9M Highway DM
$0.7M Cofferdam DM
$0.16M Materials DM
$2.2M Transmission Tower Relocation
$0.6M Lock and Navigation Models at WES
$0.2M Environmental Studies
$0.4M Construction Contracts
$0.44M Management/Miscellaneous
Subsurface exploration costs are included in the costs for the DMs above.
GENERAL
Groundbreaking - The Projects groundbreaking ceremony is scheduled for Friday, 15
October 1999 at 2:00 p.m.
Acceleration of Schedule In keeping with the Corps emphasis to reduce the
funding carryover from CG projects, the Lakes and Rivers Division (LRD) Commander, BG Hans
Vanwinkle, has sent a letter to the Nashville District (LRN) setting a goal of spending
$25M on KY Lock in FY 00. Since this is significantly higher than our current estimate for
our capability in FY 00, this will be a tremendous challenge. We will be examining all
reasonable ideas for accelerating the project. One example being considered is the
acquisition and stockpiling of materials and possibly engineered items. Any ideas for
accelerating the project should be addressed to Don Getty. A meeting for the expressed
purpose of schedule acceleration for the five ongoing navigation projects in LRD is
scheduled for 22-23 April in Cincinnati.
FY 99 Financial Status Since 31 March marked the end of the first half of the
fiscal year, it is a good time to assess how the Project is progressing from a financial
standpoint. The table below compares the actual versus scheduled status of two important
indicators as of 31 March:
Actual Scheduled
Expenditures $2.58M $2.98M
Obligations $6.13M $6.18M
We obviously have a lot of work to do over the next six months to expend a total of
$12.6M if we have only spent $2.58M over the last six months. However, we are not very far
behind the spending schedule developed back in October and modified in December (when we
increased the planned Project expenditures from $8M to $12.6M). Taking into account the
delays in the billing process from our consultants and other entities working on the
Project, we are actually very close to our scheduled expenditures. It is especially
encouraging that we are hitting our planned obligations so closely. We plan to issue
approximately 11 task orders or contract modifications over the next two months that will
significantly increase our obligations. These new design activities, the ongoing design
activities, and the planned construction activities for this summer should dramatically
accelerate the expenditures on the Project over the next six months.
C. PROGRESS FOR THE MONTH:
Exploration
The Corps Drill Crew has completed twelve of the seventeen offset holes planned
for the west bank (WB) RR alignment.
The Contract Drill Crew (H.C. Nutting Co.) completed all eight of the vertical soil
borings at the downstream guidewall and have completed three of the ten angle holes for
rock drilling.
Recent testing completed and results available for drill holes from: transmission
towers (island), proposed west bank borrow site, nine EB RR alignment holes, cemetery
access road, and EB RR bridge piers and abutment.
Near term drilling and testing schedule:
Approx. 16 April Tests results from 6 complete Vulcan borrow holes, first 8
downstream guidewall and tower holes, first 6 WB RR offset holes, and last 2 cemetery
access road holes.
29 April Completion of drilling for 17 WB RR offset holes
3 May Initiate East Bank Hwy drilling by FMSM
3 May Initiate drilling for 6 holes of EB Wye RR track
10 May Initiate drilling for remaining 14 holes at Vulcan East Strip borrow site
23 June - Initiate West Bank Hwy drilling by in-house crew
July Initiate overwater drilling by Harza for: 1) Hwy bridge piers, 2) D/S
cofferdam, 3) U/S approach walls drilled shafts, and 4) possibly downstream bent
locations for truss assembly.
Hydraulic Design
Duration and Frequency Data - Charlie Irwins (LRN) development of KY tailwater
duration and frequency elevations on a monthly basis is currently under review and should
be distributed within two weeks.
Hydrographic Survey The hydrographic survey to locate the coffer cells upstream
of KY Dam was completed the week of 22 March but equipment problems prevented the survey
of the boat basin on the downstream left bank. This survey is now scheduled for the week
of 5 April.
WES Lock Model
Modifications to accommodate the new upstream floating guardwall and new upstream
topography in the Lock Model are complete and testing has been initiated. Initial tests
indicate that the new upstream guardwall will result in an acceptable hydraulic design.
However, it was agreed in a meeting on 25 March (minutes available soon) that small
modifications to the upstream topography will be required. These tests should be complete
this spring.
WES Navigation Model
Design and construction activities are slightly ahead of schedule for this effort. A
site visit and meeting was held on 25 March to discuss progress to date and upcoming tests
(minutes available). Major construction of the model will be completed by early April 99
with testing to begin by July 99, after calibration and base conditions have been
finalized. A meeting with navigation interests will be held at WES to view the tests after
base conditions have been substantially completed, probably in the July timeframe. WES
personnel installed a third camera at KY Lock the week of 22 March for use in the impact
analysis of the new upstream guidewall.
Lock Design
In-house efforts continue to focus on the support of WESs Lock and Navigation
Model work, existing lock stability, new lock stability, miter gate design, culvert valve
design, preliminary electrical/mechanical design, east bank permanent embankment, and the
development and managing of task orders.
Electrical/Mechanical Concept Report Efforts by Harza Engineers on this feature
are proceeding well. A 70% report was submitted on schedule and a review meeting was held
on 30 March (minutes available soon).
Site Development John Manor of LRN has completed conceptual designs and drawings
of the new locks site development (available upon request). A task order is being
developed with Gresham Smith and Partners to take this conceptual design to a DM level
design. A draft scope for this effort is currently under review. It is hoped that a
kick-off meeting for this effort will be scheduled for early May at the site.
Lower Guidewall Design efforts by Harza for this feature are proceeding well.
Aggregate samples from two quarry sites were obtained on 26 March and Roller Compacted
Concrete testing is scheduled to commence on 14 April. A 30% submittal is expected in
April.
Upper Approach Walls - It is planned to issue a task order to advance the upstream
guardwall to DM level to one of EP-Ds new IDT Contractors upon their selection (see
below).
Floating Caisson A site visit with Inca Engineers to view the existing floating
caisson is planned for the week of 5 April.
Miter Gate Design Design efforts by the Louisville District Corps of Engineers
(LRL) on this feature are proceeding well. Harza engineers are using preliminary geometry
developed by LRL for the concept designs of the gate operating machinery.
As-built Drawings Preliminary efforts have been initiated by TVAs Hydro
Engineering Group for this feature. It is expected that most of the as-builts will be
complete by the end of this FY.
EB Permanent Embankment The DM level design of this feature is currently
underway by EP-G and is expected to be completed in early spring.
EP-D New IDTs - The selection process for four new specialty lock A/E contracts
is proceeding well. The first two contractors are expected to under contract in April 1999
with the remaining two following soon thereafter.
Disposal/Contractor Laydown Areas
Efforts have been initiated to more accurately determine the disposal and contractor
laydown areal requirements for the various construction features of the Project. The last
such assessment was made in the early 1990s and changes/refinements in the
Projects design have prompted this reassessment. A site visit by engineering
personnel is planned for mid-April to examine possible locations. Sites being considered
on the TVA reservation include the west bank overbank area just upstream of the boat basin
and downstream from the tailwater restroom and various smaller areas on the EB. If these
sites are considered viable, then they will be addressed in the Hwy EA. The 1992 EIS only
identified one terrestrial disposal site a site presently owned by Vulcan Materials
on the EB. Discussions have been initiated with Vulcan officials in an effort to determine
the current viability of this site.
Cofferdam DM
The task order to Harza Engineers for the design of the downstream cofferdam to a DM
level was awarded on 30 March. A kick-off meeting for this effort has not yet been
scheduled. The geotechnical design of the upstream cofferdam and the overall development
of the Cofferdam DM will be the responsibility of EP-G. It is anticipated that the
structural design of the upstream cofferdam and the grouting plan for the lock will be by
separate A/E contracts issued later this FY.
Hwy/RR
Quarterly Design Meetings The next quarterly design meeting is scheduled for
11-12 May at the Lake Barkley Resource Managers office. The RR-only meeting is scheduled
for the afternoon of 11 May. The joint Hwy/RR meeting is scheduled for the morning of 12
May and the Hwy-only meeting that afternoon. It was originally planned to have the July
quarterly meeting at WES to view the pier testing in the Navigation Model. However, it was
decided at the 25 March WES meeting to combine the testing of the bridge piers and
training dikes. Therefore, the Hwy/RR meeting at WES will be postponed, probably until the
late summer or early fall. The summer quarterly meeting will now be held at the site,
tentatively the week of 12 July. WES agreed to provide a submittal date that LRN (i.e.,
Hanson and ACE) would have to furnish the initial pier configurations for both bridges to
meet the models revised testing schedule.
Highway DM
DM Design The contract for this design effort was awarded to American Consulting
Engineers (ACE) on 30 March. ACEs efforts for the next month will concentrate in
three areas:
Determination of pier loading and pier type studies
Bike bridge layout and analysis
Urban vs. rural sections analysis and alignment studies
A task order is being prepared to have Fuller, Mossbarger, Scott and May to perform the
EB drilling and the geotechnical reports necessary for the Hwy DM.
Coordination with the Kentucky Transportation Cabinet In a phone conversation on
22 March, Mr. Charles Raymer, Deputy State Highway Engineer, agreed that the cost
limitations proposed in Secretary Codells letter of 7 December 98 would not be
adhered to by the KyTC. Therefore, the KyTC will be fully funding the expansion of the Hwy
62 relocation from a two-lane roadway to a four-lane roadway. Mr. Raymer promised a
response to LRNs letter of 30 December 1998 that will document the KyTCs
position. LRN is continuing with the drafting of a betterment sharing agreement with the
KyTC that needs to be in effect by approximately July 1999.
Railroad DM
Walker Cemetery Access Road Advertisement of the construction contract for this
road is currently scheduled for June 1999 with construction to commence by the end of this
FY. These dates could be impacted if graves are found outside the cemeterys fenced
boundaries along the proposed roads alignment. Issuance of a task order is planned
in April to an A/E firm that will attempt to determine if any graves are located in this
area.
RR Design In addition to the cemetery access road and WB utilities, Hanson
Engineers have performed the following activities over the last month: 1) studied
alternatives for the north leg of the wye track, 2) continued the preliminary design of
the truss span, 3) completed preliminary design of the approach span piers, 4) initiated
collection of information for MCACES cost estimates, and 5) initiated preliminary
foundation design for the piers.
North-Leg Wye track alternative analysis Hanson Engineers are nearing completion
of an analysis of both an eight and a nine degree curve for this wye track. Upon
completion of this study, input will be solicited from both the P&L Railway, Inc. and
Vulcan Materials in an effort to select one of the two alignments.
Modifications to Hanson Contract A scope of work for this effort is being
finalized and negotiation efforts are scheduled for the week of 12 April. Because of the
complexity and volume of extra work included in this scope for this FY, it is expected
that the RR DMs completion date will be slipped by approximately two months.
WB Utility Relocations Hanson surveyors will be returning to the site the week
of 12 April in an attempt to locate all of the affected water lines. It is hoped that
Hanson will complete the design of the water and sewer lines to a 50% level by the 11 May
quarterly meeting and it is anticipated that this construction contract will be advertised
in August. Required coordination and development of legal documents with the owners could
impact this schedule. Mr. Don Fulcher, a new attorney in LRNs Real Estate office,
has initiated these legal efforts.
Geotechnical Design Harzas 95% report for the WB DM geotechnical study is
expected to be submitted the week of 12 April. A task order to Harza to perform analyses
for the EB retaining walls and wye track geotechnical studies is planned to be issued in
mid-April. Another task order will be issued to Harza to complete geotechnical studies for
P&S on the WB embankment upon completion of the testing of the 17 WB RR offset holes.
P&L Purchase Order A purchase order is under development by LRN to reimburse
the P&L Railway for expenses incurred during the review of the design of this
relocation.
TVA Transmission Towers Relocation
Eight Upstream Towers (four on each bank) - Design efforts by TVA engineers are
proceeding, with foundation/footing designs scheduled for completion by the end of May.
TVA plans to use in-house forces to drive the piles necessary for the tower foundations on
the powerhouse island starting early this summer. It is still not known what forces will
be used to construct the concrete footings for all eight towers. TVA forces will erect the
tower steel, possibly starting the erection of one tower this FY. TVA is also examining
means to expedite this relocation.
Three Downstream Towers (69 kV) - A decision on relocating the three downstream towers
is still pending based on an updated engineering analysis being performed by Harza
Engineers in their DM level design of the downstream guidewall. The results of
Harzas analysis are expected to be included in their 30% submittal of the D/S
guidewall DM, scheduled for submission in April. A final decision on the fate of these
three towers will be made after a review of this report.
Environmental
Highway Environmental Assessment - It is now proposed that the terrestrial field survey
and entire biological assessment be completed by TVA personnel by June. Consultation with
the US Fish and Wildlife Service will commence shortly thereafter. This schedule should
allow for the preparation and completion of an Environmental Assessment prior to the
advertisement for the construction of the West Bank RR/Hwy embankment early next winter.
Coordination Meeting Tim Higgs (LRN) plans to schedule an environmental
coordination meeting on site in late April or early May with all interested parties. The
agenda will include all known areas to be included in the biological assessment (including
new disposal sites), a discussion of HTRW issues, new wetlands mapping, and
schedules/responsibilities for all permitting requirements.
Environmental Mitigation - Boat Ramp and Fishing Coffer Cell Sam Perry out of
TVAs Norris Office continues to advance the design of a new boat ramp and associated
facilities on the West Bank. He also has started examining the possibility of raising the
existing fishing coffer cell below the powerhouse to reduce its flooding potential and
increase its functionality for the fishermen. Construction of these features is planned to
be initiated this summer.
Wetlands Evaluation Starting the week of 12 April, Hanson surveyors plan to
survey in the locations of all the wetlands delineated by LRN personnel in March. Hanson
Engineers will also develop CADD mapping of the wetlands upon completion of the survey.
Miscellaneous
CADD Standards/Drawing Title Blocks LRN and TVA are continuing their efforts to
develop a drawing title block to be used for this Project. LRN is also updating the CADD
standards to be followed in the development of all drawings.
Development of Drawing Library System LRN plans to develop a library of all
drawings that can be accessed by all members of the design team. When it is complete, a
message will be sent to all design team members.
KY Lock Telephone Directory A list of all organizations and key personnel
involved in the design of this project that contains their address, phone numbers and
email addresses is available upon request to Don Getty, (615) 736-2346 [don.b.getty@usace.army.mil].
End of Report |