CEERD-HN-N
(1110-2-1150a)
MEMORANDUM FOR Commander,
U.S. Army Engineer District, Nashville,
ATTN:
CELRN-EP-H
(Mr. Ben Rohrbach)
P.O.
Box 1070, Nashville, TN 37202-1070
SUBJECT: Progress Report, Model Study of Kentucky Lock and Dam,
Tennessee River
Progress During April 2001
1. Completed all scheduled testing by 28 March. Continued preparation of
the model for extended inactivity.
2. Continued preparation of the draft final report.
Work planned for May 2001
3. Complete the draft final report, and send to CELRN for review by 31
May. Continue work on the final figures and plates while the report is
being reviewed by CELRN.
4. Enclosed is a list of updated milestones and their current status.
Contact Mr. Randy McCollum (601/634-2719) with any questions regarding this
project.
Encl
THOMAS W. RICHARDSON
Acting Director
Coastal and Hydraulics Laboratory
Model Study of Kentucky Lock
Schedule of Milestones
31 March 2001
| Milestone |
Scheduled Completion |
Actual or Percent
Complete |
| Model Designed, Constructed |
15 Apr
1999 |
12 Apr 1999 |
| Install upper pool cofferdam cells
and paint model |
30 Apr 1999 |
30 Apr 1999 |
| Calibration of Powerhouse, Spillway |
30 Jun
1999 |
23 Jul
1999 |
| Completion of Base Conditions |
15
Oct 1999 |
15 Oct 1999 |
| Installation and Evaluation of Proposed
Lock Initial Conditions |
15 Nov 1999 |
30
Nov 1999 |
| Installation and Evaluation of Proposed
Bridges |
15 Feb
2000* |
7 Mar
2000* |
|
Optimization
of Plan B-2,
Documentation,
and Collection
Of
ADV Data |
21
Jul 2000 |
19
Jul 2000 |
|
Spillway
Training Works and
Modifications
to B-2 Dike |
21
Aug 2000 |
28
Aug 2000* |
|
Calibrate
flow conditions for
Railroad
truss float-in |
8
Sep 2000 |
7
Sep 2000 |
|
Incorporate
West Bank Boat
Excavation |
15
Sep 2000 |
13
Sep 2000 |
|
Analyze
Railroad Truss
Float-in
Conditions |
29
Sep 2000 |
29
Sep 2000 |
|
Powerhouse
Isl.pier impacts |
13
Oct 2000 |
1
Nov 2000 |
|
Document
Post Project
Conditions |
3
Nov 2000 |
1
Nov 2000 |
|
Evaluate
Proposed fishing
Jetties |
17
Nov 2000 |
17
Nov 2000** |
|
Collect
velocities at bridge
Piers
with 7 tailwater elev. |
1
Dec 2000
|
29
Nov 2000** |
|
Install
D/S Cofferdam and
Evaluate
Navigation Impacts |
15
Mar 2001 |
1
Mar 2001 |
|
Evaluation
of training work and D/S Cofferdam |
31 Mar 2001 |
28 Mar 2001** |
| Draft Report |
31 May 2001 |
40%** |
| Final Report |
31 Aug 2001 |
0%** |
*Milestone date not made due to
request for velocity data collection
from sponsor.
**Milestones added and revised
based on request for additional data
collection on 6 Nov., receipt of
cofferdam plans on 1 and 28 Nov., and
request for additional work with
float-in conditions that came out of 6
December meeting and request for
additional work that came out of 7
March meeting.
|