MAIN MENU KENTUCKY LOCK ADDITION - NAVIGATION MODEL PROGRESS REPORT

KY Lock Addition Home
Up

 

10 April 2001    
CEERD-HN-N   (1110-2-1150a)                                                        

MEMORANDUM FOR  Commander, U.S. Army Engineer District, Nashville,

ATTN:  CELRN-EP-H (Mr. Ben Rohrbach)

P.O. Box 1070, Nashville, TN 37202-1070

SUBJECT: Progress Report, Model Study of Kentucky Lock and Dam, Tennessee River

Progress During March 2001

1. A meeting was held on 7 March to demonstrate the model with the cofferdam plans and discuss aspects of the cofferdam design with representatives from U.S. Army Engineer Research and Development Center's Coastal and Hydraulics Laboratory (CHL), your District (LRN), TVA, the navigation industry, and members of the AE firms designing the cofferdam. As a result of the demonstration of the up-bound navigation conditions associated with the completed cofferdam plan and operation of the 300,000 cfs, 328.0 ft tailwater flow condition, CHL was requested to demonstrate the navigation conditions that would result from installing the training work on the west side of the Powerhouse Island developed for Plan B-2 (completed project with proposed 1,200-ft lock and 1,200-ft landward guide wall installed). The training work was installed, demonstrated, and appeared to provide improved navigation conditions.

2. During the presentations and discussions of the various aspects of the cofferdam construction and the potential effects to navigation, the representatives of the navigation industries agreed that the training work developed for the completed project appears to provide navigation benefits that would be beneficial throughout the construction of the project. The LRN stated that this training work could be installed at almost any point of the construction, especially if it is demonstrated that it would provide navigation benefits. The LRN requested that CHL evaluate and document the navigation conditions with the installation of the training work and the cofferdam.

3. A request for additional funding to cover the costs of the evaluation of the floating "camels" on the cofferdam float-in wall sections, evaluation of navigation conditions with the cofferdam and the Powerhouse Island training work, and "mothballing" the model to prepare it for extended inactivity was sent to LRN on 8 March. We received additional funding on 19 March.

4. In an e-mail message, dated 19 March 2001, you requested that we evaluate navigation conditions with the complete cofferdam and the training work at only 300,000 cfs, 328.0 TW, and after placement of both float-in cofferdam wall segments with only the 100,000 cfs, 306.3 TW. These evaluations were completed on 28 March. This completes all scheduled testing.

5. During a telephone conversation on 22 March between Mr. Randy McCollum of CHL and Mr. Don Getty of LRN and you, CHL was requested to provide LRN the monthly charge required to maintain an inactive model. This charge would be $1,286.00 per month.

Work Planned for April 2001

6. At present there is no additional work scheduled for the model. The model will be prepared for extended inactivity.

7. Preparation of the final report will begin.

8. A list of updated milestones and their current status is enclosed. If you have any questions regarding this project, please contact Mr. Randy McCollum at (601) 634-2719

.

Encl            THOMAS W. RICHARDSON 

                   Acting Director 

                   Coastal and Hydraulics Laboratory

 


Model Study of Kentucky Lock
Schedule of Milestones
31 March 2001 

Milestone Scheduled Completion Actual or Percent Complete
Model Designed, Constructed 15 Apr 1999 12 Apr 1999
Install upper pool cofferdam cells and paint model 30 Apr 1999 30 Apr 1999
Calibration of Powerhouse, Spillway 30 Jun 1999 23 Jul 1999
Completion of Base Conditions 15 Oct 1999 15 Oct 1999
Installation and Evaluation of Proposed Lock Initial Conditions 15 Nov 1999 30 Nov 1999
Installation and Evaluation of Proposed Bridges 15 Feb 2000* 7 Mar 2000*

Optimization of Plan B-2,

Documentation, and Collection

Of ADV Data

21 Jul 2000 19 Jul 2000

Spillway Training Works and

Modifications to B-2 Dike

21 Aug 2000 28 Aug 2000*

Calibrate flow conditions for

Railroad truss float-in

8 Sep 2000 7 Sep 2000

Incorporate West Bank Boat

Excavation

15 Sep 2000 13 Sep 2000

Analyze Railroad Truss

Float-in Conditions

29 Sep 2000 29 Sep 2000

Powerhouse Isl.pier impacts

13 Oct 2000 1 Nov 2000

Document Post Project

Conditions

3 Nov 2000 1 Nov 2000

Evaluate Proposed fishing

Jetties

17 Nov 2000 17 Nov 2000**

Collect velocities at bridge

Piers with 7 tailwater elev.

1 Dec 2000

29 Nov 2000**

Install D/S Cofferdam and

Evaluate Navigation Impacts

15 Mar 2001 1 Mar 2001

Evaluation of training work and D/S Cofferdam

31 Mar 2001 28 Mar 2001**
Draft Report 31 May 2001 0%**
Final Report 31 Aug 2001 0%**

*Milestone date not made due to request for velocity data collection from sponsor. 

**Milestones added and revised based on request for additional data collection on 6 Nov., receipt of cofferdam plans on 1 and 28 Nov., and request for additional work with float-in conditions that came out of 6 December meeting and request for additional work that came out of 7 March meeting.


Points of Contact: 

Questions about this page:

Project Manager - Don Getty (615) 736-2346

Public Affairs - Public Affairs Officer (615) 736-7161

Questions about this website:
Webmaster


Page Last Updated:
27 July 2011

Privacy and Security Notice
Information Quality Act (IQA)
Freedom of Information Act (FOIA)
Disclaimer