|
FINAL
Minutes of Meeting
With Potential Aggregate & Riprap Suppliers
New Kentucky Lock Project
9:00 AM 27 July 2001
The meeting started with all attendees introducing themselves.
(See attendees list below)
Everyone was informed that minutes of the meeting would be
produced and after attendees had a chance to review a draft, they would be
posted on the Kentucky Lock web site. The reason for the web site posting is to
make all information discussed in the meeting available to any suppliers not in
attendance. This is required to maintain the integrity of the government
procurement process.
The purpose of the meeting was stated as an opportunity to
provide potential aggregate suppliers a status on the Nashville District's
materials testing program for Kentucky Lock, provide a ballpark estimate of
quantities of materials anticipated to be used on the project, and to inform
suppliers of requirements in existing solicitation specifications and
anticipated requirements for future solicitations. It was stressed that any
quantities discussed were preliminary and subject to change because they were
based on preliminary and evolving designs. The Nashville District also wanted to
hear from the quarries about possible production problems, cost consequences, or
other concerns with providing aggregates and riprap for the project.
The goal of the Corps materials testing program was stated as
"To ensure an adequate supply of materials are available that will provide the
highest quality project at an acceptable cost."
At this point Tommy Haskins, Corps Geologist, thanked quarry
representatives present for their cooperation to date in providing material
samples used in the Kentucky Lock testing program. In return, they are being
sent the test information pertinent to their quarry as soon as it is received.
He asked if the quarries had reviewed the specs for the two projects that were
out. Rogers and Martin had not, Vulcan had. The specs are available on the web
at the Nashville District contract site, electronic bids, and solicitations.
Suppliers would then need to register as suppliers/subcontractors to download or
receive a CD of the specs, and to get emails concerning amendments. The
specifications for these projects are the vanguard of the rest of the work, with
the primary feature being the main lock chamber. Tommy went on to explain the
Corps process and guidance for conducting the materials testing program. He
explained the production of the Materials Design Memorandum and the Independent
Technical Review (ITR) process. The ITR team will consist of non-design Corps
employees, TVA, and consultants. He also described the Corps procedure of
Construction personnel taking responsibility for the specifications from
Engineering once a construction contract is awarded.
A spreadsheet summarizing anticipated concrete aggregate
quantities was provided to attendees. (See attached tables with aggregate
quantities for concrete and table with stone quantities other than concrete.) A
summary of riprap quantities was not available for the meeting. (Post meeting
Note: The current estimate of riprap quantities for all KY Lock contracts is
approximately 95,000 tons.) There is approximately 600,000 cubic yards of
concrete anticipated for the total Kentucky Lock project. This will require in
the neighborhood of 760,000 tons of coarse aggregate and approximately 300,000
tons of fine aggregate. Attendees were not interested in hearing the approximate
amounts for the individual mixes.
The Corps has embarked on two suites of materials testing at
Waterways Experiment Station (WES). The first suite is essentially complete and
results are being summarized. The second suite, started to confirm some earlier
results and to investigate some remediation measures, is ongoing. The first
suite has limited some zones of potential approved sources of the quarries,
which will be better detailed by the second suite. The results of the second
suite of sampling will affect the riprap and aggregate from the quarries. Vulcan
benches 3,4,8, and 9, Martin bench B (C was closed when went back to sample, it
is now reopened), and Rogers benches B and C are currently being tested.
Tommy noted the Corps would be available to meet with the
quarries individually so they could discuss quarry specifics that they may not
want to discuss in front of their competition. Vulcan representatives requested
to meet immediately after the ongoing meeting, and Rogers Group and Martin
Marietta indicated they would like a future meeting after they had additional
time to review the specifications.
There are currently two construction contract solicitations on
the street. One of these, the Upstream Cofferdam contract, will have an
amendment reflecting changes to the aggregate specifications. The amendment will
reflect less stringent aggregate requirements since all applications in this
contract are temporary. The Bridge Substructure contract aggregate
specifications are essentially State of Kentucky specs with additional limits on
chert content (coarse-10%, fine-35%), alkali-carbonate reactivity, and specific
gravity (coarse -2.6, fine-2.55). For the float-in walls, the specs will be more
stringent; because the life span desired for the project is 100 years. It is
very important to minimize chances for reactions from a alkali-silica or
alkali-carbonate standpoint.
It was noted that the lock structure contract shall be the
most stringent specifications for the project.
Vulcan asked about the RCC mix and was informed it no longer
being considered for use in the main lock chamber, but is anticipated to be used
in the lower guidewall. There is approximately 36,000 CY of RCC using 50,000
tons aggregate in the lower guidewall.
Quality control tests, tests for a new fourth quarry, and
other optional tests have been built into the existing versions of the
specifications as bid items. If a quarry gets into a new area, these optional
tests can be called for. Also, the contractor will likely have to pay for
testing in a new area of the quarry. Vulcan representatives stated the
contractor usually expects the quarry to pay for these tests. Quality control
testing in the Substructure contract is currently scheduled to be performed
every 15,000 tons. With the addition of the Boat Basin to the project, the total
quantity of riprap will be approximately 27,000 tons which would require 2
quality control tests.
It is impossible to test everything in the quarry. Parts of
the quarry are not available for testing, if the operations change, it might be
necessary to build new tests into the construction specs. Some areas can only be
reached by coring, which might be done for potential ledges.
We anticipate using a "3 inch" aggregate mix for the
lock. Gradation expected is as follows:
100% ----------- 4"
90 - 100%------- 3"
20 - 55%-------- 2"
0 - 10%--------- 1 ½"
0 - 5%---------- 1"
Quarry representatives didn't anticipate having a problem meeting
this gradation requirement.
Attendees:
Johnny Parham COE (615) 736-7839
Melanie Leslie COE (615) 736-7526
Tommy Haskins COE (615) 736-7901
Tram Pollock COE (615) 736-7927
Ron Carter COE (615) 736-5024
Paul Ross COE (615)
736-5685
Johnny Boyd MMA (270) 554-0804
Vernon Gilland MMA (270) 556-0304
Russell Mann RGI (270) 886-3344
Gary Doom VMC (270) 362-4264
Chuck Marek VMC (205) 298-3217
Terry Teitloff VMC (270) 362-1282
James Niznik TVA (423) 751-7082
Don Getty COE (615) 736-2346
Tony Ellis COE (270) 362-2163
Emily Carr COE (615) 736-7882
Dale Driskill VMC (270) 362-1232
2 Attached:
Concrete & Grout Summary Table
Stone Other Than Concrete Summary Table
Click the charts below to
view the full-sized image.

Concrete &
Grout Summary Table

Stone Other
Than Concrete Summary Table
|