Corps
Design Team Nominated for Hammer AwardA team of design
engineers, led by the U.S. Army Corps of Engineers, has been nominated for the Hammer
Award, Vice President Al Gores program for re-inventing government.
Kentucky Lock is located at Mile 22 on the Tennessee River. The 110 x 600
lock has experienced long delays over the past years as a result of an inadequate lock
chamber size. A 1992 Feasibility Report recommended a new 110 x 1200 lock
adjacent to the existing lock. The original cost was estimated to be $540 Million.
In 1994 the Ohio River Division office initiated a three-phase cost-reduction plan for
navigation projects aimed at reducing the total cost of projects in the Ohio River Basin.
At that time the Kentucky Lock Team was in the process of collecting data on the existing
lock and starting preliminary site planning on the new lock. In order to meet the
objectives of the Divisions cost reduction plan, the team quickly changed gears and
began looking for possible savings which could be realized by revising the traditional
lock designs used in the Feasibility Report.
Working together in a partnership with the A-E joint venture of Harza and Parsons
Brinckerhoff and the navigation industry, the team began a six-month process of
brainstorming and innovative design. In the fall of 1994 the team identified $11 million
in the 1st phase of innovative design which resulted from lowering of the contingency for
foundation preparation. This reduction was a direct result of a well-thought-out
exploration program that gave designers a better understanding of the foundation
conditions.
After the 1st phase work was complete, the team began breaking the feasibility designs
apart in an effort to find other areas where potential savings existed. The team used a
systematic approach to prioritize and categorize the savings areas. Large, complex areas
were studied by several team members from different sections or branches, while some
small, less complex areas were handled by one individual. When necessary, the navigation
industry was consulted for input on the effect of any proposed changes. Several open
briefings were also conducted for the navigation industry to update them on design
changes, and answer any questions they might have. The final redesign included relocating
the footprint of the lock to reduce required excavation, building in the wet guidewalls,
and major redesigns of some of the locks larger components. The Kentucky Lock
Teams 2nd phase effort resulted in an additional savings of $81 million.
The 3rd phase of innovative design looked at more complex, less-proven design changes.
This phase required a more in-depth design effort and some model testing to prove the
design changes would work. Some of the major changes resulting from this effort included a
"thru sill" intake system which has not been used on a modern lock, roller
compacted concrete in the lock chamber walls and guidewalls, and a discharge system which
greatly reduced the required amount of costly temporary cofferdam. The total savings from
this phase are estimated to be $23 million.
The cost reduction efforts came at a time when Kentucky Lock was being criticized for
costing too much. Some members of the navigation industry who openly questioned the need
for the project prior to the cost reductions now say they endorse the lower-priced
project. The navigation industry has applauded the Districts commitment and effort
to reduce the cost of this project, and the teams commitment to this task has
significantly improved the projects chances of being authorized and funded in the
future. These savings could only have been identified by a team dedicated to the cost
reduction philosophy and the project as a whole.